Rooftop Solar PV Grid Interactive System (Third Amendment) Regulations, 2024 — Finalization Order

In the matter of finalization of the Himachal Pradesh Electricity Regulatory Commission (Rooftop Solar PV Grid Interactive System) (Third Amendment) Regulations, 2024.

OrderDated 12 Jun 2024Published in the Gazette 16 May 2024

Made under the Rooftop Solar PV Grid Interactive Systems based on Net Metering Regulations, 2015.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Commission's order of 12 June 2024 finalizing and approving the Third Amendment to its Rooftop Solar PV Grid Interactive System Regulations (p1, p5). Pages 1–2 give the background: the 2015 principal net-metering regulations (Rajpatra, 3 August 2015), their first and second amendments (2018 and 2022, the latter renaming them), and the trigger for this amendment — the Ministry of Power's notification G.S.R.125(E) of 22 February 2024 amending the Electricity (Rights of Consumers) Rules, 2020 to exempt rooftop solar systems up to 10 kW from the technical feasibility study. The draft third amendment was notified on 13 May 2024 and gazetted on 16 May 2024 under s.181(1) of the Electricity Act 2003 (p1).

Pages 2–3 record the consultation: press notices on 19 May 2024, a 31 May 2024 deadline for objections, letters to major stakeholders, and a public hearing on 3 June 2024, with written submissions from HPSEBL and the BBNIA.

Pages 3–5 contain the decisions. The Commission replaces Table-1 and Table-2 under Regulation 5(2), which cap permissible rooftop solar capacity by sanctioned connected load and by supply voltage level respectively (p4). It inserts a new Regulation 5(4) so that systems up to 10 kW need no technical feasibility study, sanctioned load is deemed enhanced to the plant capacity where short, charges follow the 2012 Recovery of Expenditure Regulations, and security deposit follows the 2005 Security Deposit Regulations (p4). It inserts "where required" into Regulation 7(3) on feasibility checking (p4–5). It declines HPSEBL's requests to mandate email/WhatsApp intimation and to replace "net meter" with "smart net meter" (p3), and rejects BBNIA's suggestion on verifying captive rooftop generation, pointing to the RPPO Regulations 2023 (p5). Annexure-A (p6) lists who attended the hearing.

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, New connections and load changes, Metering

Read with this

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.