APERC · Andhra Pradesh Electricity Regulatory Commission
Regulation 11 of 2025 — First Amendment
Regulation 11 of 2025 First Amendment
AmendmentDated 4 Dec 2025Published in the Gazette 8 Dec 2025
Amends the Regulation 6 of 2025.
Summary
Summary written by software. Check the regulator's original before you rely on it.
On 4 December 2025 the Andhra Pradesh Electricity Regulatory Commission issued the first amendment to its Green Energy Open Access, Charges and Banking Regulation, 2024 (Regulation No. 3 of 2024); it was published in the AP Extraordinary Gazette on 8 December 2025 (p1, p11). The amendment rewrites the working core of that regulation and carries a worked illustration as its annexure.
The introduction (pp1–4) records the trigger: the Government of Andhra Pradesh's Integrated Clean Energy Policy, 2024, conveyed by the Special Chief Secretary/Energy under section 108 of the Electricity Act, 2003, with the policy's targets, technology list and investment ambitions. A draft amendment went out with a public notice on 26 March 2025; comments were received, a revised draft was circulated, and the final amendment follows an order of 4 December 2025.
The operative clauses (pp4–11) replace the definition of "banking" and let EV charging stations buy input power through a green energy open access generator; replace the connectivity and energy-settlement clause with block-wise settlement, banking of over-injection and under-drawal, inadvertent-energy treatment and deviation rules for RE generators; replace the treatment of existing and new entities, grandfathering open access agreements signed before the principal regulation; set metering rules including a smart-meter requirement for LT open access; replace standby charges and their duration; add cross-subsidy and additional-surcharge exemptions for green hydrogen, solar module/wind turbine and battery manufacturing; and replace the banking cycle, the 30% cap on banked energy, and the time-of-day rules for banking and drawal. The final clause protects agreements from later amendments.
The Annexure (pp12–16) is a numerical illustration of block-wise settlement, the banking cap, banking charges and time-of-day settlement, with a disclaimer that the regulation prevails over it.
Read with this
The regulation
- Dated 11 Sep 2025Regulation 6 of 2025
Amendments and corrections
- Dated 24 Feb 2025Regulation No.3 of 2025 — Third Amendment
- Dated 24 Feb 2025Regulation No.1 of 2025 — Third Amendment
- Dated 24 Feb 2025Regulation No. 2 of 2025 — Fourth Amendment to the Electricity Supply Code Regulation
- Dated 11 Jul 2025Regulation No.4 of 2025 — Fourth Amendment to the Licensees' Duty for Supply of Electricity on Request and Recovery of Expenses Regulation, 2013
- Dated 9 Oct 2025Licensees and Standards of Performance Regulation, 2004 — Sixth Amendment, 2025
- Dated 4 Dec 2025Regulation 8 of 2025 — Second Amendment
- Dated 4 Dec 2025Grid Interactive Solar Rooftop Photovoltaic Net/Gross Metering Regulation, 2023 — First Amendment, 2025
- Dated 5 Dec 20251st Amendment through Reg No 12 of 2025
- Dated 5 Dec 2025Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulation, 2025 — First Amendment, 2025 — Statement of Reasons
- Dated 8 Jan 2026Grid Interactive Solar Rooftop Photovoltaic Systems under Net/Gross Metering Regulation, 2023 — First Amendment, 2025 — Errata
- Dated 8 May 2026Regulation No 03 of 2026 — Second Amendment
- Dated 8 May 2026Renewable Energy Tariff Determination Regulation, 2025 — Second Amendment, 2026 — Statement of Reasons and Order
- Dated 30 Jul 2026Regulation No.5 of 2026 — Fifth Amendment
Commencement notices and reasons
- Dated 11 Sep 2025RE Tariff Determination Regulation, 2025 — Statement of Reasons
Consolidated copies, for reference (1)
Other copies of these documents (1)
Earlier drafts
Voltaic last read APERC's website for final documents on 24 Nov 2026 (2 pages) and for drafts on 21 Nov 2026. A document APERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.