MERC · Maharashtra Electricity Regulatory Commission

Grid Interactive Rooftop Renewable Energy Generating Systems Regulations, 2019 — Draft

Maharashtra Electricity Regulatory Commission (Grid Interactive Rooftop Renewable Energy Generating Systems) Regulations, 2019

Draft regulationReleased with the notice dated 26 Oct 2019

Draft

A proposal that has since been finalised as the Grid Interactive Rooftop Renewable Energy Generating Systems Regulations, 2019.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the draft of the Maharashtra Electricity Regulatory Commission (Grid Interactive Rooftop Renewable Energy Generating Systems) Regulations, 2019 — the framework that would replace the Commission's 2015 rooftop solar net metering regulations, extending to the whole of Maharashtra and taking effect from publication in the Official Gazette (p1).

Definitions and scope come first (p1–5, Regs 1–2): net metering, net billing, banked energy, the Eligible Consumer, metering and settlement vocabulary. Part A (p5–6, Regs 3–5) sets general conditions — both arrangements granted non-discriminatorily on a first-come-first-served basis at transformer/feeder level, net metering reserved for residential consumers, and a cumulative ceiling on renewable capacity per distribution transformer with a proviso requiring the licensee to exceed it absent an adverse load study, plus quarterly publication of available headroom.

Part B (p6–11, Regs 6–10) is the technical block: who may be an Eligible Consumer and at what individual capacity, interconnection standards and safety, anti-islanding, synchronisation and harmonic requirements, metering infrastructure (net meter, renewable energy generation meter, check meters), the web-based application and approval procedure with its timelines, and the connection agreement.

Part C (p12–16, Regs 11–15) handles money: net metering energy accounting for residential consumers with a first tranche netted at retail tariff, banking of surplus and purchase of the balance at generic tariff; net billing as a bundled purchase by the licensee at generic tariff, expressed as a billing equation; meter-failure accounting; RPO treatment; REC ineligibility; and exemption from wheeling, banking, cross-subsidy and transmission charges.

Part D (p16–17, Regs 16–20) gives the Commission powers to relax, issue orders and practice directions, amend and remove difficulties, and repeals the 2015 net metering regulations with savings for systems already commissioned. Annexures 1–6 (p18–31) supply the application procedure, model application form and checklist, model net metering and net billing connection agreements, the behind-the-meter prior-intimation form, and the transformer-capacity reporting format.

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Net billing, Metering

Read with this

Other copies of these documents (1)

7 more documents belong here and are not on Voltaic: 5 drafts or notices on a draft not held as English text, 1 copy in another language and 1 draft or notice on a draft.

Voltaic last read MERC's website for final documents on 28 Nov 2026 (8 pages) and for drafts on 28 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on merc.gov.in ↗

Report an issue with this document