Grid Interactive Rooftop Renewable Energy Generating Systems Regulations, 2026 — Draft

Maharashtra Electricity Regulatory Commission (Grid Interactive Rooftop Renewable Energy Generating Systems) Regulations, 2026

Draft regulationReleased with the explanatory memorandum dated 22 Sep 2026No. MERC / Tech /Regulation/2026 /____ dated __ September 2026

Draft

A proposal, not law. Voltaic holds no final regulation made from this draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The document is a draft MERC regulation that would replace the 2019 grid-interactive rooftop framework and consolidate net metering, net billing, group net metering, gross metering, virtual net metering and behind-the-meter systems in Maharashtra (p1, p6, p29). It extends to the whole State and is to commence on publication in the Official Gazette, with transitional rules for applications made after the draft and for capacity augmentation (p1).

Part A, Regulations 3–5, sets the scope and general conditions: the arrangements covered, capacity limited by contract demand or sanctioned load, non-discriminatory first-come-first-serve connectivity, an energy-storage obligation for larger new systems, limits on switching between arrangements, treatment of consumers with arrears, priority for open-access settlement, and a distribution-transformer capacity cap that can be exceeded after a load study (pp6–9).

Part B, Regulations 6–10, covers technical arrangements: eligible-consumer and project capacity, interconnection to CEA standards, islanding and harmonic requirements, inverter data sharing, metering infrastructure and check meters, the online application and registration-fee process with service timelines, and a 20-year connection agreement supported by model forms (pp9–15).

Part C, Regulations 11–14, is the commercial core. It prescribes bill disclosures and energy accounting for net metering, group net metering, virtual net metering, net billing and gross metering; a banking framework keyed to Contracted RE Capacity, with a small-consumer annual banking window and slot-based monthly banking with fixed and variable charges above it (pp16–27); accounting for meter defects; and allocation of RPO credit (pp27–28).

Part D, Regulations 15–19, gives the Commission powers to relax, issue directions, amend and remove difficulties, and repeals the 2019 Regulations and their 2023 and 2024 amendments with savings for existing agreements and migration options (pp29–30). The annexures provide application forms, model connection agreements, a prior-intimation form, a transformer-capacity reporting format and a VNM application form (pp31–54).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Energy banking, Energy accounting and settlement

Read with this

Other copies of these documents (1)

7 more documents belong here and are not on Voltaic: 5 drafts or notices on a draft not held as English text, 1 copy in another language and 1 draft or notice on a draft.

Voltaic last read MERC's website for final documents on 28 Nov 2026 (8 pages) and for drafts on 28 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.