RE Tariff Third Amendment Regulations, 2015 — Statement of Reasons

The Central Electricity Regulatory Commission (Terms and Conditions for Tariff determination from Renewable Energy Sources) (Third Amendment) Regulations, 2015

Statement of reasonsDated 10 Jul 2015

Replaced by RE Tariff Regulations, 2017

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2012 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Central Commission's Statement of Reasons for the Third Amendment to the RE Tariff Regulations, 2015, signed at New Delhi on 10 July 2015 (p1, p5). It records why the Commission amended the normative operating norms for biomass-based power projects, and it is the interpretive record that tariff analysts should read alongside the amending regulations themselves.

Section 1 sets the background (p1): the second amendment of 5 January 2015, made on MNRE's recommendation, allowed biomass projects to use fossil fuel up to 15% of calorific value on an annual basis. In that earlier Statement of Reasons the Commission had itself flagged that the normative Station Heat Rate was set assuming 100% biomass and that permitting fossil fuel could affect it, and had directed staff to examine the issue. After a staff analysis, a draft Third Amendment was published on 16 April 2015; three stakeholders commented in writing and a public hearing was held on 5 May 2015.

Section 2 frames the two issues taken up: the normative Station Heat Rate (SHR) and the normative Gross Calorific Value (GCV) of the fuel mix for biomass projects (p2). Section 3 reproduces the proposed substitution of Regulation 38 (SHR), records stakeholder objections — coal logistics and scarcity in Punjab, open-market coal prices, CDM restrictions on fossil fuel use, and state pollution-control consents that bar any fuel other than agro-residue — and gives the Commission's decision (p2–3). The Commission declined to carve out Punjab or any state on the ground that SERCs are mandated to decide for their own states, and retained the substitution, but qualified it so that the specified SHR applies to biomass projects using fossil fuel up to 15% of calorific value annually.

Section 4 does the same for Regulation 43 (GCV of fuel), with a parallel Punjab-specific plea to retain the pre-amendment GCV and bar fossil fuel; that plea was also rejected as a state-specific matter, and the substitution was retained with the same 15% fossil-fuel qualifier (p3–4). Section 5 records two further suggestions — extending the revised technical norms to already-operating old plants, and clarity on whether the extra coal fuel cost would be reflected in variable cost when the Commission fixes generic tariffs — and states that both fall outside the scope of this exercise and were not considered (p4–5).

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff

Read with this

Other copies of these documents (5)

Earlier drafts

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.