RE Tariff Regulations, 2012 — Statement of Objects and Reasons

Statement of Objects and Reasons CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2012 (06.02.2012)

Statement of reasonsDated 6 Feb 2012

Replaced by RE Tariff Regulations, 2017

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2012 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software, from pages 1 to 47 of 123. Check the regulator's original before you rely on it.

The document is the Statement of Objects and Reasons for the CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2012 (p1). It is not the regulation itself: it explains why the Commission framed the 2012 RE tariff framework, records stakeholder consultation, and sets out the Commission's reasoning on draft provisions. Pages 2-3 give the legal basis under the Electricity Act, 2003, the earlier RE Tariff Regulations 2009, the prior control period ending 31.03.2012, the draft public notice of 18.11.2011, the comment deadline of 15.12.2011 and the public hearing of 22.12.2011, and list commenters in Annexure-I.

Pages 4-9 deal with definitions and eligibility. They reproduce draft definitions of useful life, installed capacity and inter-connection point, summarise stakeholder objections, and record the Commission's decisions, including retaining the useful-life definition, clarifying pooling sub-station, limiting cogeneration to non-fossil fuels, simplifying wind eligibility, defining topping cycle and declining a lower solar capacity threshold.

Pages 10-19 cover general principles: control period, tariff period, project-specific tariff, generic tariff design and discount factor, and despatch principles. They record the decision to keep a control period with a mid-period biomass price review, to allow PPAs beyond the minimum tariff period, to allow project-specific tariffs for new and other technologies, and to retain must-run treatment while applying IEGC-2010 scheduling to larger biomass and solar plants.

Pages 20-42 cover financial principles. They set out the Commission's decisions on debt-equity, loan tenure and interest, depreciation, return on equity, working capital, O&M expenses, CDM benefit sharing, subsidies and incentives (including MNRE Central Financial Assistance tables), and taxes and duties.

Pages 43-47 begin the technology-specific norms for wind energy. They record the debate on wind capital cost, the Commission's cost build-up, and its decision to revise the capital cost norm in the final regulations.

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff, Tariff determination, Capital cost and investment

Read with this

Other copies of these documents (5)

Earlier drafts

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.