CERC · Central Electricity Regulatory Commission
Indian Electricity Grid Code Regulations, 2023
Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2023
Regulation · Gazette copyDated 29 May 2023Published in the Gazette 11 Jul 2023No. L-1/265/2022/CERC.— dated 29th May, 2023
The Gazette copy of the Indian Electricity Grid Code Regulations, 2023.
Summary
Summary written by software, from pages 1 to 121 of 185. Check the regulator's original before you rely on it.
This is the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2023, published in the Gazette of India, Extraordinary, Part III Section 4 (p1). It is notified under s.79(1)(h) read with s.178(2)(g) of the Electricity Act 2003 (p103). The preamble (pp102–103) sets out the statutory division of labour between the CEA (grid standards), the Commission (grid code and quality, continuity and reliability standards), NLDC, RLDCs, RPCs, CTU/STUs, SLDCs, generating companies and licensees, and records that State Commissions must frame State Grid Codes consistent with this Code.
The notification is dated 29 May 2023 (p102) and the Gazette issue 11 July 2023 (p1). Commencement is deferred: the regulations take effect from a date the Commission notifies, and different dates may be fixed for different regulations (p103). No commencement date is printed.
Chapter 1 (pp103–111) gives the short title, the scope — all users, SLDCs, Renewable Energy Management Centres, RLDCs, NLDC, CTU, STUs, licensees, RPCs, Settlement Nodal Agencies, Qualified Coordinating Agencies and power exchanges — treats DVC as a regional entity and separate control area, BBMB and SSP stations as regional entities, and any inter-connected country as a separate control area, and defines over 130 terms, many by cross-reference to other CERC and CEA instruments.
Chapter 2, the Resource Planning Code (pp111–112), lays out integrated resource planning: distribution licensees' demand estimation across long, medium and short horizons, State-level aggregation by the STU, generation resource adequacy and procurement planning, an annual NLDC national simulation to assist States, a planning reserve margin framed by CEA, and demonstrable adequacy targets approved by SERCs backed by a non-compliance charge.
Chapter 3, the Connection Code (pp113–114), specifies technical and design criteria for connectivity (granted by CTU under the GNA Regulations), the standards users must comply with, the procedure for first-time energization, connectivity agreements, a joint system study six months ahead of energization, and data and communication facilities.
Chapter 4, the Protection Code (pp114–117), requires a uniform regional protection protocol developed by each RPC, annual review of protection settings with a centralised database, internal annual and five-yearly third-party protection audits, monthly reporting of dependability, security and reliability indices, System Protection Scheme design and review, and disturbance recorder and event logger requirements.
Chapter 5, the Commissioning and Commercial Operation Code (pp117–121), specifies start-up power and infirm power drawal and injection windows, their charges and stop-supply triggers; the data to be furnished before notice of trial run (Table 1, p118); notice and conduct of trial run; trial-run rules for thermal, hydro, wind/solar/ESS/hybrid units and for transmission elements; and the OEM documents and tests required before declaration of commercial operation.
Read with this
The regulation
- Dated 29 May 2023Indian Electricity Grid Code Regulations, 2023
Amendments and corrections
- Dated 23 Oct 2024Indian Electricity Grid Code (First Amendment) Regulations, 2024
Commencement notices and reasons
- Dated 3 Aug 2023Gazette – effective date 1.10.2023
- Dated 3 Aug 2023Notification – effective date 1.10.2023
- Dated 2 Aug 2024Indian Electricity Grid Code Regulations, 2023 — Statement of Reasons
Procedures and orders made under it
- Dated 28 Sep 2023Detailed Procedure for Assessment of Secondary & Tertiary Reserve Capacity — Approval Order, 28 September 2023
- Dated 30 Sep 2023Indian Electricity Grid Code Regulations, 2023 — Removal of Difficulties (First Order)
- Dated 18 Dec 2023Indian Electricity Grid Code Regulations, 2023 — Removal of Difficulties (Second Order)
- Dated 16 Apr 2024Detailed Procedure for SCUC, USD and SCED at Regional Level, 2024 — Approval Order under Indian Electricity Grid Code Regulations, 2023
- Dated 22 Dec 2024Indian Electricity Grid Code Regulations, 2023 — Third Removal of Difficulties Order, 2024
- Dated 12 Feb 2025Black Start Support Payment Procedure
- Dated 12 Mar 2025Detailed Procedure for MTL Support through SCED for Section 62 Generators, IEGC Regulations 2023 — Approval Order, 2025
Other copies of these documents (1)
- Dated 23 Oct 2024Indian Electricity Grid Code (First Amendment) Regulations, 2024
Proposed changes (drafts with no final yet)
- Dated 21 Sep 2026Indian Electricity Grid Code (Second Amendment) Regulations, 2026 — Draft
- Dated 21 Sep 2026Explanatory memorandum: Draft IEGC Second Amendment Regulations, 2026 — Explanatory Memorandum
- Dated 21 Sep 2026Public notice: Draft Indian Electricity Grid Code (Second Amendment) Regulations, 2026 — Public Notice
- Dated 22 Oct 2026Notice extending the date for comments: Indian Electricity Grid Code (Second Amendment) Regulations, 2026 — Extension of last date for comments — Public Notice
- Dated 22 Oct 2026Hearing notice: Public hearing notice on Draft Indian Electricity Grid Code (Second Amendment) Regulations, 2026
Earlier drafts
- Dated 7 Jun 2022Indian Electricity Grid Code Regulations, 2022 — Draft
- Dated 7 Jun 2022Public notice: Draft Indian Electricity Grid Code Regulations, 2022 — Public Notice
- Dated 30 Aug 2022Notice extending the date for comments: Draft Indian Electricity Grid Code Regulations, 2022 — Extension of comment deadline to 30.09.2022
- Dated 29 Sep 2022Notice extending the date for comments: Public Notice — Extension of Comments Deadline on Draft Indian Electricity Grid Code Regulations, 2022
- Dated 29 Sep 2022Hearing notice: Public hearing on Draft Indian Electricity Grid Code Regulations, 2022
- Dated 9 Oct 2022Explanatory memorandum: Draft Indian Electricity Grid Code Regulations, 2022 — Explanatory Memorandum
- Dated 18 Oct 2022Notice extending the date for comments: Draft Indian Electricity Grid Code Regulations, 2022 — Extension of comment deadline to 31.10.2022 — Public Notice
- Dated 12 Jun 2024Indian Electricity Grid Code Regulations, 2023 — First Amendment, 2024 — Draft
- Released with the notice dated 12 Jun 2024Explanatory memorandum: Indian Electricity Grid Code, 2023 — First Amendment, 2024 — Explanatory Memorandum — Draft
- Dated 12 Jun 2024Public notice: Indian Electricity Grid Code (First Amendment) Regulations, 2024 — Public Notice — Draft
- Dated 31 Jul 2024Hearing notice: Public hearing notice — Draft Indian Electricity Grid Code (First Amendment) Regulations, 2024
6 more documents belong here and are not on Voltaic: 4 drafts or notices on a draft not held as English text and 2 drafts or notices on a draft.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.