CEA Recommendations on Operation Norms for Thermal Generating Stations — DeSOx/DeNOx, Tariff Period 2019-24

CERC Terms and Conditions of Tariff for the tariff period starting from 01.04.2019 CEA Recommendations on Operation Norms for thermal generating stations

Annexure or form of a draftDated 20 Feb 2019CEA/TETD-TT/2019/N-15/ 266 dated 20.2.2019

Draft

The draft has since been finalised as the Terms and Conditions of Tariff (First Amendment) Regulations, 2020.

Annexure or form of the Terms and Conditions of Tariff (First Amendment) Regulations, 2020 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a letter from the Central Electricity Authority's Thermal Engineering & Technology Development Division dated 20 February 2019, forwarding additional CEA recommendations on operation norms for thermal generating stations. It is directed at the CERC exercise on Terms and Conditions of Tariff for the tariff period beginning 1 April 2019, and continues an earlier CEA letter of 10 December 2018 that covered the general operation norms for 2019-24 (p1).

The substance sits in Annexure-1 (pp2–11). It opens by restating the SO2 and NOx emission limits notified by MoEF&CC on 7 December 2015, grouped by the date a unit was installed, and explains that because no operating data on DeSOx/DeNOx systems existed in the country at the time, the norms were worked out from utility, OEM and consultant inputs and pilot studies (p2).

Part A (pp2–8) covers DeSOx. It gives an empirical formula for admissible limestone consumption in wet limestone FGD, with a coefficient that changes according to which SO2 norm the unit must meet; a single admissible lime (CaO) consumption figure for lime spray dryer / semi-dry FGD; a single sodium bicarbonate figure for dry sorbent injection; and a formula for limestone injected into CFBC furnaces. Each is supported by assumptions (removal efficiency, stoichiometric ratio, reagent purity, conversion factor) and comparisons with utility/OEM data. Part A also prescribes auxiliary energy consumption norms, as percentages of gross generation, for wet limestone, sea-water and semi-dry FGD, plus an extra allowance where a GGH is provided, and no norm at all for dry sorbent injection.

Part B (pp8–10) does the same for DeNOx: urea consumption for SNCR units meeting the 300 mg/Nm3 norm, ammonia consumption for SCR units meeting the 100 mg/Nm3 norm, and an additional auxiliary energy allowance for the SCR pressure drop.

The closing Recommendations section (pp10–11) consolidates the admissible reagent and auxiliary energy norms and says they should be reviewed once sufficient operational data is available.

Standard name
Tariff Regulations
Primary topics
Emission control costs

Read with this

The regulation

Procedures and orders made under it

Other copies of these documents (3)

Earlier drafts

8 more documents belong here and are not on Voltaic: 4 drafts or notices on a draft and 4 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document