GERC · Gujarat Electricity Regulatory Commission
Net Metering Rooftop Solar PV Grid Interactive Systems, 2016 — Fifth Amendment, 2025 — Explanatory Memorandum — Draft
Explanatory Memorandum
Explanatory memorandum to a draftDated 14 Oct 2025
Draft
The draft has since been finalised as the Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Fifth Amendment, 2025.
Explanatory memorandum to the Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Fifth Amendment, 2025 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Commission's explanatory memorandum accompanying the draft Fifth Amendment to the GERC (Net Metering Rooftop Solar PV Grid Interactive Systems) Regulations, 2016. It opens (p1) by reciting the principal regulations and the four earlier amendments — 2017, 2020, 2022 and 2024 — and identifies the two provisions it proposes to change: the activity chart under Regulation 7 and the connectivity levels under Regulation 8(2).
The first change responds to Petition No. 2475 of 2025, filed by four state-owned DISCOMs, and to an MNRE letter of 31.12.2024 asking for a simplified net metering process. The memorandum reproduces a proposed third proviso to Regulation 7 (p1–2) under which no separate written connectivity agreement would be executed for rooftop systems installed under PM Surya Ghar Muft Bijli Yojana; the consumer would be deemed bound by the regulations, the agreement would be deemed to commence on the date of commissioning, and the DISCOM would instead issue a written communication under proper receipt stating that date and the applicable surplus energy purchase rate.
The second change (p2–3) proposes replacing the existing Regulation 8(2) connectivity-level table with a cross-reference to the GERC (Electricity Supply Code and Related Matters) Regulations, 2015 and its amendments, so that rooftop connectivity levels track the Supply Code. The memorandum explains that the Supply Code was amended on 23.09.2024 to permit LT connectivity up to 100 kVA/kW of contracted demand, or up to 150 kVA/kW where the applicant opts for it, and that Regulation 8(2) must be aligned. The document closes (p3) with the proposed replacement text for Regulation 8(2).
Read with this
The regulation
Amendments and corrections
- Dated 6 Oct 2017Net Metering Rooftop Solar PV Grid Interactive Systems (First Amendment) Regulations, 2017
- Dated 23 Jan 2020Net Metering Rooftop Solar PV Grid Interactive Systems (Second Amendment) Regulations, 2020
- Dated 31 May 2022Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Third Amendment, 2022
- Dated 4 Sep 2024Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Fourth Amendment, 2024
- Dated 3 Nov 2025Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Fifth Amendment, 2025
Commencement notices and reasons
- Dated 5 Oct 2017Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — First Amendment, 2017 — Statement of Reasons
- Dated 23 Jan 2020Net Metering Rooftop Solar PV Grid Interactive Systems, 2016 — Second Amendment, 2020 — Statement of Reasons
- Dated 31 May 2022Net Metering Rooftop Solar PV Grid Interactive Systems (Third Amendment) Regulations, 2022 — Statement of Reasons
- Dated 4 Sep 2024Net Metering Rooftop Solar PV Grid Interactive Systems, 2016 — Fourth Amendment, 2024 — Statement of Reasons
- Dated 4 Nov 2025Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Fifth Amendment, 2025 — Statement of Reasons
Proposed changes (drafts with no final yet)
Earlier drafts
- Dated 31 Jan 2016Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Draft
- Dated 13 Jun 2017Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — First Amendment, 2017 — Draft
- Dated 18 Dec 2019Net Metering Rooftop Solar PV Grid Interactive Systems, 2016 — Second Amendment, 2019 — Draft
- Dated 29 Jun 2021Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Third Amendment, 2021 — Draft
- Dated 18 May 2024Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Fourth Amendment, 2024 — Draft
- Dated 18 May 2024Explanatory memorandum: Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Amendment — Explanatory Memorandum
- Dated 14 Oct 2025Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Fifth Amendment, 2025 — Draft
5 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft and 2 copies in another language.
Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.