Net Metering Rooftop Solar PV Grid Interactive Systems (Second Amendment) Regulations, 2020

Gujarat Electricity Regulatory Commission (Net Metering Rooftop Solar PV Grid Interactive Systems) (Second Amendment) Regulations, 2020

AmendmentDated 23 Jan 2020Notification No. 2 of 2020 dated 23/01/2020

Replaced by Grid Interactive Distributed Renewable Energy Sources Regulations, 2026

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on gercin.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Second Amendment to the GERC (Net Metering Rooftop Solar PV Grid Interactive Systems) Regulations, 2016 (the Principal Regulations), issued as Notification No. 2 of 2020 and signed 23/01/2020 (p14). It extends to the whole of Gujarat and takes effect from the date of publication in the Official Gazette, which is not printed in the text (p1).

It inserts a new definition of MSME (Manufacturing) Enterprise into Regulation 2.1, tying eligibility to registration under the MSMED Act, 2006 and reproducing the investment-in-plant-and-machinery thresholds (p2), and amends Regulation 5 to cap the cumulative rooftop capacity at a distribution transformer to the transformer's own capacity (p3).

Regulation 6.2 is amended to set the eligible system size: 50% of sanctioned load/contract demand for most consumers, with no such limit for residential consumers and MSME (Manufacturing) Enterprises (p3–4). References to GEDA are broadened to "GEDA or agency designated by the Government of Gujarat", and the protection-system sub-activity is rewritten to require anti-islanding and a second line of protection for systems above 10 kW (p4).

Regulation 9 on Energy Accounting and Settlement is wholly replaced (pp4–9). It creates separate settlement sub-regimes by consumer class and by whether the consumer uses the 'energy attribute', the 'renewable attribute' for RPO, or REGs — residential/government, industrial/commercial other than MSME, MSME (Manufacturing), RPO-compliance consumers, and REC consumers. It fixes surpluses rates, banking within one billing cycle, 15-minute time-block accounting for certain categories, and year-end crediting (pp4–9).

Metering (Regulation 13.5) is replaced with accuracy classes, mandatory check meters above 20 kW, and cost/testing responsibilities (pp9–10); the two net metering configuration diagrams are deleted (p10). Annexure IV clauses 7(A)(ii), 7(B)(a)(ii), new 7(B)(a)(iii), 7(B)(b)(ii), 7(B)(c)(ii) and 1.3 are amended to align interconnection agreements with the new settlement and capacity rules (pp10–14).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Energy banking, Metering

Read with this

Proposed changes (drafts with no final yet)

5 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft and 2 copies in another language.

Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.