GERC · Gujarat Electricity Regulatory Commission

Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Fifth Amendment, 2025

Gujarat Electricity Regulatory Commission (Net Metering Rooftop Solar PV Grid Interactive Systems) (Fifth Amendment) Regulations, 2025

AmendmentDated 3 Nov 2025Published in the Gazette 3 Nov 2025Notification No. 10 of 2025; GERC/2025/10/Tech/2201 dated 03/11/2025

Replaced by Grid Interactive Distributed Renewable Energy Sources Regulations, 2026

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on gercin.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

A two-page amendment by the Gujarat Electricity Regulatory Commission to its 2016 net metering rooftop solar regulations. Gazetted on 3 November 2025 as Notification No. 10 of 2025, it is the Fifth Amendment, extends to the whole of Gujarat and takes effect from publication in the Official Gazette — the date the document itself prints, 3 November 2025 (p1).

It makes two changes. Attached to the Activity Chart under Regulation 7 of the Principal Regulations (as read with the Fourth Amendment of 2024), a new proviso removes the need for a separate written connectivity agreement between the distribution licensee and the consumer where solar rooftop PV is installed under PM Surya Ghar Muft Bijli Yojana. The consumer is deemed bound by the regulations, the agreement is treated as commencing on the date of commissioning, and the discom must instead communicate to the applicant that commencement date together with the applicable rate for purchase of surplus energy (p2).

Regulation 8(2) is substituted so that the voltage level at which a rooftop system connects to the grid follows the GERC (Electricity Supply Code and Related Matters) Regulations, 2015, rather than being fixed in these regulations (p2).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering

Read with this

Proposed changes (drafts with no final yet)

5 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft and 2 copies in another language.

Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.