Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016 — Third Amendment, 2022

Gujarat Electricity Regulatory Commission (Net Metering Rooftop Solar PV Grid Interactive Systems) (Third Amendment) Regulations, 2022

AmendmentDated 31 May 2022NOTIFICATION NO. 02 OF 2022 dated 31/05/2022

Replaced by Grid Interactive Distributed Renewable Energy Sources Regulations, 2026

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, 2016.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on gercin.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is GERC's Third Amendment to its 2016 Net Metering Rooftop Solar PV Grid Interactive Systems Regulations, notified as Notification No. 02 of 2022 and signed at Gandhinagar on 31/05/2022 (p1, p21). It takes effect from the date of publication in the Official Gazette; no Gazette date is printed (p1). It does not restate the 2016 Regulations — it rewrites named regulations and, unusually, prints the full substituted text of the energy-accounting regulation plus a model interconnection agreement.

Pages 1–3 rebuild the definitions: sanctioned/contracted load is redefined, "Eligible Consumer" is widened to include third-party sale, "Gross Meter" and "gross-metering" are added alongside a rewritten "net-metering", and "prosumer" and "third party" are introduced (p2–3). Scope and general principles are extended from net metering to gross metering and from consumers to prosumers (p3–4), and the capacity-target regulation is broadened to match.

The core practical change is the capacity window in Regulation 6.2: net metering for projects of 1 kW and above up to 1000 kW, and gross metering for projects above 10 kW up to 1000 kW, with installed capacity aligned to the Supply Code and the Intra-State Open Access Regulations (p6). Capacity rules for residential, captive, third-party, REC and RPO projects follow (p7).

Regulation 9 is replaced wholesale (p7–18): billing and accounting must show injection, supply, net billed energy and net export separately; energy injected before commissioning is treated as inadvertent power with no compensation; and projects commissioned under earlier net metering regulations keep their old accounting unless capacity or contracted load changes. Five sub-regimes then set accounting granularity and surplus-injection compensation — residential and government consumers (p9–11), captive use (p11–14), third-party sale (p14–16), REC mechanism (p16–17) and RPO compliance (p17–18) — together with banking charges, time-of-day set-off windows and the treatment of excess drawal. Regulation 12 adds captive-use treatment for transmission charges, wheeling and cross-subsidy/additional surcharges (p18–19), and a new metering clause permits non-ABT meters for consumers up to a contracted-load threshold (p19). New penalty provisions 16.1–16.3 cover replacement of damaged modules, unauthorised capacity addition and unapproved connectivity (p19–21). Annexure-I adds an abbreviation (p22), and a model interconnection agreement (pp23–39) sets eligibility, technical, metering, settlement, liability, dispute and termination terms for licensees to adapt.

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Gross metering, Energy accounting and settlement

Read with this

Proposed changes (drafts with no final yet)

5 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft and 2 copies in another language.

Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.