Himachal Pradesh Electricity Supply Code, 2009 — Sixth Amendment, 2025

Himachal Pradesh Electricity Supply (Sixth Amendment) Code, 2025

AmendmentDated 17 Mar 2025In force from 1 Apr 2025No. HPERC/Supply Code/438 dated 17th March, 2025

Amends the Himachal Pradesh Electricity Supply Code, 2009.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

Notification No. HPERC/Supply Code/438, dated 17 March 2025, makes the sixth set of amendments to the Himachal Pradesh Electricity Supply Code, 2009, and comes into force on 1 April 2025 (p1). It is twelve amending paragraphs that rewrite definitions, voltage-wise connection rules, service timelines, metering and billing practice, and disconnection grounds in the Principal Code.

Paras 2 and 3 amend the definitions and the Code's own amendment machinery: new definitions of 'Accuracy' (tied to CEA regulations under s.55 of the Act) and of a Resident Welfare Association, plus a proviso allowing the Commission to align the Code with Ministry of Power rules without a recommendation of the Supply Code Review Panel (p1–2).

Para 4 is the largest change, rewriting para 2.1.6.1 on standard supply voltage: a substituted voltage/connected-load/contract-demand table, a special domestic-category ceiling, a reduced special-category load limit, and a staged transitional regime for existing consumers on lower-than-standard voltage — LVSS to 01.04.2026, then compounding incremental charges, with permanent disconnection as the endpoint after 01.03.2027. It also defines 'dedicated feeder' and 'special category loads' and deletes two sub-paras (p2–4).

Paras 5–9 amend connection and service timelines (area-wise periods including hilly terrain, shortened completion timelines), remove the test report requirement for transfer of title or change of name of a deceased consumer, link performance-standard breaches to the 2010 Distribution Performance Standards Regulation, and insert new paras 3.1A and 3.1B — a special regime for Resident Welfare Associations (single-point versus individual connections decided by ballot, separated metering and billing, no-profit-no-loss resale) and separate supply connections for EV charging (p4–7).

Paras 10–12 cover metering and enforcement: a verification meter on complaint about meter reading, overhauling of accounts where errors stem from wrong CT/PT connections or multiplication factors, smart-meter maximum-demand billing with automatic sanctioned-load reset, deemed delivery of e-mailed bills, and a new disconnection ground for failure to switch to standard voltage with a carve-out for smart prepayment meters (p7–8).

Standard name
Electricity Supply Code
Primary topics
Conditions of supply, New connections and load changes, Metering

Read with this

The regulation

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document