HP Electricity Supply Code, 2009 — Release of Electricity Connections under Two Part Tariff — Finalization of List of Documents

Himachal Pradesh Electricity Supply Code, 2009, as amended from time to time,-Release of the electricity connections covered under two part tariff-Finalization of list of documents under Sub-para (3.1.2) of para 3.1 of said Code.

OrderDated 24 Aug 2022

Made under the Himachal Pradesh Electricity Supply Code, 2009.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Himachal Pradesh Electricity Regulatory Commission's order of 24 August 2022 finalising the list of documents an applicant must file to get a new electricity connection billed on two-part tariff (pp1-2). The Commission acts under Sub-para (3.1.2) read with item (3.1.2.2) of Para 3.1 of the HP Electricity Supply Code, 2009 — which reserves the specification of that list to the Commission — and under Regulation 67 of its Conduct of Business Regulations, 2005 (p2). The Code was notified on 26 May 2009 and published in the Rajpatra on 29 May 2009, and has been amended five times, most recently by publication on 21 January 2022 (p1).

Objections were invited through newspaper notices on 23 July 2022 and the proposal was posted on the Commission's website; industry and hoteliers associations, the Department of MPP & Power, the Directorate of Energy and the distribution licensee were asked to respond by 20 August 2022 (pp1-2). No comments came, so the Commission adopted the proposed list unchanged (p2).

Annexure-A (pp3-4) is the operative content. It groups the documents into: general papers (application and agreement form, licensed contractor's test report, power availability certificate, Chief Electrical Inspector approval for HT/EHT energisation, project report for industrial connections, registration or single-window clearance, and statutory and pollution-board NOCs); photo identity proof; proof of ownership or occupancy; and extra requirements for partnership firms, companies and trusts. Notes let the licensee demand further documents to protect its legal and financial interests — publishing that list to field officers and on its website — and adapt the requirements for a change of name.

Annexure-I (pp5-6) prescribes the undertaking a consumer files on plain paper where a statutory NOC cannot be produced, allowing release under the temporary metered supply category, with regularisation only after the completion plan sanction letter is submitted.

Standard name
Electricity Supply Code
Primary topics
New connections and load changes

Read with this

The regulation

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document