HPERC · Himachal Pradesh Electricity Regulatory Commission
HP Electricity Supply Code, 2009 — Release of Electricity Connections under Two Part Tariff — Finalization of List of Documents
Himachal Pradesh Electricity Supply Code, 2009, as amended from time to time,-Release of the electricity connections covered under two part tariff-Finalization of list of documents under Sub-para (3.1.2) of para 3.1 of said Code.
OrderDated 24 Aug 2022
Made under the Himachal Pradesh Electricity Supply Code, 2009.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Himachal Pradesh Electricity Regulatory Commission's order of 24 August 2022 finalising the list of documents an applicant must file to get a new electricity connection billed on two-part tariff (pp1-2). The Commission acts under Sub-para (3.1.2) read with item (3.1.2.2) of Para 3.1 of the HP Electricity Supply Code, 2009 — which reserves the specification of that list to the Commission — and under Regulation 67 of its Conduct of Business Regulations, 2005 (p2). The Code was notified on 26 May 2009 and published in the Rajpatra on 29 May 2009, and has been amended five times, most recently by publication on 21 January 2022 (p1).
Objections were invited through newspaper notices on 23 July 2022 and the proposal was posted on the Commission's website; industry and hoteliers associations, the Department of MPP & Power, the Directorate of Energy and the distribution licensee were asked to respond by 20 August 2022 (pp1-2). No comments came, so the Commission adopted the proposed list unchanged (p2).
Annexure-A (pp3-4) is the operative content. It groups the documents into: general papers (application and agreement form, licensed contractor's test report, power availability certificate, Chief Electrical Inspector approval for HT/EHT energisation, project report for industrial connections, registration or single-window clearance, and statutory and pollution-board NOCs); photo identity proof; proof of ownership or occupancy; and extra requirements for partnership firms, companies and trusts. Notes let the licensee demand further documents to protect its legal and financial interests — publishing that list to field officers and on its website — and adapt the requirements for a change of name.
Annexure-I (pp5-6) prescribes the undertaking a consumer files on plain paper where a statutory NOC cannot be produced, allowing release under the temporary metered supply category, with regularisation only after the completion plan sanction letter is submitted.
Read with this
The regulation
- Dated 26 May 2009Himachal Pradesh Electricity Supply Code, 2009
Amendments and corrections
- Dated 11 Jun 2014Himachal Pradesh Electricity Supply Code, 2009 — First Amendment, 2014
- Dated 31 Jul 2018Himachal Pradesh Electricity Supply Code, 2009 — Second Amendment Regulations, 2018
- Dated 3 Dec 2018Himachal Pradesh Electricity Supply Code, 2009 — Third Amendment, 2018
- Dated 3 Jul 2020Himachal Pradesh Electricity Supply Code, 2009 — Fourth Amendment, 2020
- Dated 14 Jan 2022Himachal Pradesh Electricity Supply Code, 2009 — Fifth Amendment, 2021
- Dated 17 Mar 2025Himachal Pradesh Electricity Supply Code, 2009 — Sixth Amendment, 2025
Commencement notices and reasons
- Dated 12 Nov 2012H.P. Electricity Supply Code Review Panel Constitution Notification, 2012
- Dated 9 Jun 2014Himachal Pradesh Electricity Supply Code (First Amendment) Regulations, 2014 — Order
- Dated 3 Jul 2020Himachal Pradesh Electricity Supply Code, 2009 — Fourth Amendment, 2020 — Finalisation Order
- Dated 17 Mar 2025Himachal Pradesh Electricity Supply Code, 2009 — Sixth Amendment, 2024 — Finalization Order
Procedures and orders made under it
- Dated 27 Mar 2009Disconnection of Supply upon Detection of Theft of Electricity Notification, 2009
- Dated 22 Mar 2016Reconstitution of Electricity Supply Code Review Panel, 2016
- Dated 13 Dec 2019Electricity Supply Code Review Panel Reconstitution Notification, 2019
- Dated 27 Jul 2022Reconstitution of the Electricity Supply Code Review Panel, 2022
- Dated 3 Jul 2026Electricity Supply Code Review Panel Reconstitution Notification, 2026
Proposed changes (drafts with no final yet)
Earlier drafts
- Dated 23 Jan 2018Himachal Pradesh Electricity Supply Code, 2009 — Second Amendment, 2018 — Draft
- Dated 30 Jan 2018Explanatory memorandum: Himachal Pradesh Electricity Supply Code, 2009 — Second Amendment, 2018 — Explanatory Memorandum — Draft
- Dated 20 Jan 2020Himachal Pradesh Electricity Supply Code, 2009 — Fourth Amendment, 2020 — Draft
- Dated 18 Oct 2021Himachal Pradesh Electricity Supply Code, 2009 — Fifth Amendment, 2021 — Draft
- Dated 10 Oct 2024Himachal Pradesh Electricity Supply Code, 2009 — Sixth Amendment, 2024 — Draft
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.