RE Tariff Regulations, 2017 — Second Amendment, 2019 — Order

In the matter of amendment of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) (Second Amendment) Regulations, 2019.

OrderDated 24 Jan 2019Published in the Gazette 7 Aug 2018

Made under the Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software, from pages 1 to 23 of 37. Check the regulator's original before you rely on it.

This is HPERC's order finalising the Second Amendment to its 2017 RE tariff regulations, following the State Government's 15 May 2018 amendment to the Hydro Power Policy 2006. The order records why the Commission proposed changes — mainly to delink small-hydro tariff from the date of signing the Implementation Agreement and to align with the amended state policy — and then works through objections received (pp1–3).

Pages 1–3 set out the procedural history: the 2017 RE Tariff Regulations, the State Government's section 108 advice to modify regulation 11, the draft Second Amendment Regulations published in August 2018, newspaper notices, stakeholder letters, and the public hearings that were rescheduled twice before being held on 3 November 2018 (pp1–3). Annexure A lists hearing participants (p3).

Pages 3–5 summarise the objections and issues raised at the public hearing by developers, associations, the Directorate of Energy, HPSEBL and the consumer representative. These cover the control period, zero date/SCOD, CUF, open access charges, royalty power, tariff methodology, purchase obligations and consumer burden (pp3–5).

The Commission refuses to make the 2017 regulations retroactive to 1 April 2017 and keeps regulation 1's proposed wording (pp5–6). It finalises definitions for the control period and for 'Government Designated Agency/Designated Agency', adding certification and implementation functions and allowing different agencies for different SHP categories (pp6–7). It drops the proposed definition of 'Scheduled COD' and finalises a 'Zero Date' definition tied to the State Hydro Policy or separate state notification (pp7–8). It retains regulation 3's applicability restrictions, declining to reopen concluded PPAs (pp8–9).

On regulation 8, it drops the condition that a PPA can be approved only after zero date and instead allows the distribution licensee to grant in-principle approval for purchase of SHP power within the state policy framework, with validity and lapse conditions (pp9–11). It enlarges the first control period to 30 September 2019 rather than the proposed longer date, after stakeholders objected (pp11–13). It omits regulation 11 prospectively, rejecting HPSEBL's plea to retain it (pp13–14). It finalises the substitution of regulation 14 but incorporates the revised control period (pp14–15). On regulation 13 and proposed regulation 14-A, it accepts stakeholders' objections: the Commission drops the proposed SCOD/COD determination and extension mechanism, notes inconsistent COD definitions in the two model IAs, and substitutes regulation 13 with tariff linked to the date of commencement of operation, using that term rather than COD (pp15–23).

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff, Tariff determination, Power procurement and PPAs

Read with this

One more document belongs here and is not on Voltaic: a draft or notice on a draft.

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.