Promotion of Generation from RE Sources and Tariff Determination (Sixth Amendment) Regulations, 2023 — Finalisation Order

Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) (Sixth Amendment), Regulations, 2023

OrderDated 27 Jan 2023

Read with the Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Himachal Pradesh Electricity Regulatory Commission's order of 27 January 2023 (p1) finalising the Sixth Amendment to its 2017 RE Tariff Regulations. It is the Commission's reasoned decision on the draft amendment it issued on 28 November 2022 and published in the Rajpatra on 1 December 2022 (p1) — not the amendment text itself, which is not reproduced.

The trigger is the Ministry of Power's Electricity (Late Payment Surcharge and Related Matters) Rules, 2022, gazetted on 3 June 2022, together with a Ministry clarification of 13 September 2022 that Rules prevail over regulations in case of conflict (p1). The Commission decided to align its RE framework with those Rules and made the amendment retrospective from 3 June 2022, directing that PPAs approved on or after that date be aligned, and that the distribution licensee and RE generators file a joint petition by 31 March 2023 for a supplementary PPA or modification of approval (p3).

Paras 1–8 (p1–2) record the consultation: newspaper notices, comments due 2 January 2023, a public hearing on 7 January 2023, and letters to stakeholders including small hydro developers' associations, the Directorate of Energy, HIMURJA and the distribution licensee. HPSEBL and HPPCL responded; HPPCL treated its objections as nil (p2).

Para 9 (p2–4) sets out HPSEBL's three submissions and the Commission's responses: the interaction of the second and third provisos of draft Regulation 31-BB on payment security and the RE generator's right to sell contracted power on the power exchanges; the absence of a definition of Outstanding Dues; and alignment with the LPS Rules. The Commission accepted the need for a redraft and a definition, and decided to add provisions compensating RE generators for losses on market sale and a Green Day Ahead Market price floor (p3–4). The regulations were finalised, approved and ordered to be notified as the Sixth Amendment Regulations, 2023 (p4).

Standard name
Renewable Energy Tariff Regulations
Primary topics
Late payment surcharge and rebate, Payment security, Power procurement and PPAs

Read with this

One more document belongs here and is not on Voltaic: a draft or notice on a draft.

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.