Deviation Settlement Mechanism (Third Amendment) Regulations, 2026 — Explanatory Memorandum — Draft

Draft Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) (Third Amendment) Regulations, 2026

Explanatory memorandum to a draftDated 16 Jun 2026No. L-1/260/2021/CERC dated 16.06.2026

Explanatory memorandum to the Deviation Settlement Mechanism and Related Matters (Third Amendment) Regulations, 2026 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's explanatory memorandum (No. L-1/260/2021/CERC, dated 16.06.2026) accompanying the draft DSM (Third Amendment) Regulations, 2026 — a consultation document setting out why six changes to the Deviation Settlement Mechanism Regulations, 2024 are proposed, each with the draft amendment clause quoted. Comments are invited by 26 June 2026 (p10).

Section 1 (p2) recounts the parent regulation's history: the DSM Regulations, 2024 notified 5 August 2024 and in force from 16 September 2024 except Regulation 8(8); the First Amendment (17 December 2024, effective 23 December 2024) dealing with infirm power; the Second Amendment (25 June 2025, effective 1 July 2025) on fuel cost recovery during thermal testing. It records the representations from RE associations and ESS developers, and a Grid India communication on the payment schedule, that prompted the present draft.

Section 2 (p3–5) proposes replacing the time-block weighted average ACP of IDAM in the definitions of 'Contract Rate' and 'Reference Charge Rate' with a daily weighted average ACP, for third-party open access and captive generating plants — a methodology simplification, not a rate change.

Section 3 (p5–6) responds to the Commission's Suo Motu Order of 31 March 2026 and aligns deviation charges for Wind-Solar Sellers with those for General Sellers, phased by two thresholds: bid or tendering dates on or after 01.01.2027, and commercial operation on or after 01.01.2029 for other projects.

Section 4 (p6–7) fixes how deviation charges are computed for standalone pumped-hydro storage ESS whose tariff is determined under Section 62, where neither a contract rate nor a reference charge rate exists, by tying them to the energy charge rate in the Tariff Regulations, 2024.

Section 5 (p8–9) creates a limited payment for infirm power injected by standalone ESS between first synchronisation and the successful trial run, at the normal deviation rate with a ceiling of Rs. 2.00/kWh, with consequential amendments to the zero-payment clauses.

Section 6 (p9–10) makes consequential amendments to Regulation 10 so that payment timelines follow the NLDC Detailed Procedure for the National Deviation and Ancillary Services Pool Account rather than fixed 10-day periods.

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Energy accounting and settlement, Energy storage deployment

Read with this

Other copies of these documents (4)

Earlier drafts

9 more documents belong here and are not on Voltaic: 6 drafts or notices on a draft not held as English text, 2 drafts or notices on a draft and 1 procedure or order made under it.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.