Deviation Settlement and Related Matters (Third Amendment) Regulations, 2026 — Statement of Reasons

Central Electricity Regulatory Commission (Deviation Settlement and Related Matters) (Third Amendment) Regulations, 2026 - Statement of Objects & Reasons (SOR) thereof.

Statement of reasonsDated 25 Aug 2026No. L-1/260/2021/CERC dated 25th August 2026

The commission's reasons for the Deviation Settlement Mechanism and Related Matters Regulations, 2024 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Central Electricity Regulatory Commission's Statement of Objects and Reasons for the third amendment to the DSM Regulations, 2024, issued on 25 August 2026 (p1). It records the consultation on the draft amendment, comments from 41 stakeholders, and a public hearing on 30 June 2026, then gives the Commission's final rulings (p2). The Commission decided the third amendment will take effect on 31 August 2026, not the 1 July 2026 proposed in the draft (p3).

On definitions, CERC rejected the draft change to Contract Rate and Reference Charge Rate for open-access/captive sellers from the time-block weighted average ACP of the Integrated Day-Ahead Market to a daily weighted average ACP. It retained the existing time-block provisions in Regulations 3(1)(j)(iii) and 3(1)(y)(iii) (pp3–7).

On wind-solar sellers, CERC retained new Regulation 8(4A), which brings WS sellers within General Seller deviation-charge treatment for projects with tendering or bid submission on or after 1 January 2027 and other projects with commercial operation on or after 1 January 2029 (pp7, 14–15). It rejected grandfathering and deferral arguments; operational aspects at mixed pooling stations are to be developed by Grid India, with CERC approval, before 1 January 2029 (pp14–15).

On storage, CERC retained a Note after Regulation 8(5) requiring deviation charges for standalone pumped hydro storage under Section 62 to be computed on the energy charge rate under Regulation 66(3) of the CERC Tariff Regulations, 2024, with a review after two years through a separate order (pp16–18). It also retained the draft amendments for standalone ESS infirm power: Regulation 8(2A) pays normal deviation charges subject to a ₹2.00/kWh ceiling, with consequential changes to Regulation 8(1) and 8(4) (pp18–22).

On payment timelines, CERC declined to replace the 10-day statutory period with the NLDC Detailed Procedure; instead it inserted a flexibility clause allowing the Commission-approved Detailed Procedure timeline alongside the existing 10-day requirement, retaining late payment surcharge (pp22–26). Other stakeholder suggestions on frequency caps, pool recovery, forecasting reports, ramp rates and related matters were held outside the scope (pp26–28). Annexure I lists 41 commenters (pp29–30) and Annexure II lists public-hearing presenters (p31).

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Energy storage deployment, Energy accounting and settlement

Read with this

Other copies of these documents (4)

Earlier drafts

9 more documents belong here and are not on Voltaic: 6 drafts or notices on a draft not held as English text, 2 drafts or notices on a draft and 1 procedure or order made under it.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document