Promotion of Generation from Renewable Energy Sources and Tariff Determination (Fourth Amendment) Regulations, 2020 — Draft
Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) (Fourth Amendment) Regulations, 2020
Published with a draftDated 23 Mar 2020No. HPERC/428. dated 23rd March, 2020
Draft
The draft has since been finalised as the Promotion of Generation from RE Sources and Tariff Determination Regulations, 2017 — Fourth Amendment, 2020.
Published with the Renewable Energy Tariff Fourth Amendment Regulations, 2020 — Modifications to draft — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a draft notification by the Himachal Pradesh Electricity Regulatory Commission publishing proposed Fourth Amendment Regulations to its 2017 RE tariff regulations for objections and suggestions (p1–2). The recitals say the existing control period and the Central Commission's RE regulations end on 31 March 2020, and that the Commission first proposed extending the control period to 30 September 2020 but curtailed it to 31 March 2020 on stakeholder request to align with CERC; it now proposes a third control period from 1 April 2020 (p1).
The draft regulations would come into force on 1 April 2020, but objections are invited for 60 days from publication in the Rajpatra (p1–2). Clause 2 amends regulation 9 to provide that the small hydro third control period runs from 1 April 2020 to 31 March 2025 (p2). Clause 3 inserts a Part III on financial principles into Chapter IV, specifying capital-cost scope and exclusions, treatment of subsidy, incentive and generation-based incentive, debt-equity, loan and finance charges, depreciation, return on equity, working capital for different technology groups, O&M expenses, taxes and duties, rebates, late payment surcharge, ceiling norms and application to all RE technologies (p2–8).
Clause 4 inserts a Part III on small hydro technology parameters into Chapter V: capacity categories, normative capital cost, CUF-based saleable energy, free-power structure and adjustment formula, auxiliary/transformation losses, project-line losses, O&M norms and capacity rounding (p8–11). Clause 5 makes consequential reference substitutions in the 2017 Regulations (p12). This is a draft; no repeal, savings or final notification is stated.
Read with this
The regulation
Amendments and corrections
- Dated 7 May 2018Promotion of Generation from Renewable Energy Sources and Tariff Determination (First Amendment) Regulations, 2018
- Dated 28 Jan 2019Promotion of Generation from Renewable Energy Sources and Tariff Determination (Second Amendment) Regulations, 2019
- Dated 11 Nov 2019Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017 — Third Amendment, 2019
- Dated 8 Sep 2020Promotion of Generation from RE Sources and Tariff Determination Regulations, 2017 — Fourth Amendment, 2020
- Dated 20 Nov 2020Promotion of Generation from Renewable Energy Sources and Tariff Determination (Fifth Amendment) Regulations, 2020
- Dated 27 Jan 2023Promotion of Generation from RE Sources and Tariff Determination Regulations, 2017 — Sixth Amendment, 2023
- Dated 22 Sep 2023Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017 — Seventh Amendment, 2023
- Dated 24 Jun 2026Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017 — Eighth Amendment, 2026
Commencement notices and reasons
- Dated 15 Nov 2017Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017 — Statement of Reasons
- Dated 7 May 2018Promotion of Generation from RE Sources and Tariff Determination Regulations, 2017 — First Amendment, 2018 — Order
- Dated 19 Nov 2020RE Tariff Regulations, 2017 — Fifth Amendment, 2020 — Statement of Reasons
- Dated 27 Jan 2023Promotion of Generation from RE Sources and Tariff Determination (Sixth Amendment) Regulations, 2023 — Finalisation Order
- Dated 22 Sep 2023Promotion of Generation from RE Sources and Tariff Determination Regulations, 2017 — Seventh Amendment, 2023 — Finalisation Order
- Dated 23 Jun 2026RE Tariff Regulations, 2017 — Eighth Amendment, 2026 — Finalization Order
Procedures and orders made under it
- Dated 24 Jan 2019RE Tariff Regulations, 2017 — Second Amendment, 2019 — Order
- Dated 11 Nov 2019Promotion of Generation from RE Sources and Tariff Determination (Third Amendment) Regulations, 2019 — Order
- Dated 8 Sep 2020Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017 — Fourth Amendment, 2020 — Order
Earlier drafts
- Dated 11 Aug 2017Draft RE Tariff Regulations, 2017
- Dated 29 Mar 2018Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017 — First Amendment, 2018 — Draft
- Dated 1 Aug 2018Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination (Second Amendment) Regulations, 2018 — Draft
- Dated 31 Jul 2019RE Tariff Regulations, 2017 — Third Amendment, 2019 — Draft
- Dated 6 Oct 2020Promotion of Generation from Renewable Energy Sources and Tariff Determination (Fifth Amendment) Regulations, 2020 — Draft
- Dated 28 Nov 2022RE Tariff Regulations, 2017 — Sixth Amendment, 2022 — Draft
- Dated 20 Jul 2023RE Tariff Regulations, 2017 — Seventh Amendment, 2023 — Draft
- Dated 20 Jul 2023Explanatory memorandum: Renewable Energy Tariff (Seventh Amendment) Regulations, 2023 — Draft Explanatory Memorandum
- Dated 12 May 2026Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017 — Eighth Amendment, 2026 — Draft
- Dated 3 Jul 2020File: Renewable Energy Tariff Fourth Amendment Regulations, 2020 — Modifications to draft — Draft
One more document belongs here and is not on Voltaic: a draft or notice on a draft.
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.