Draft GERC (Electricity Supply Code and Related Matters) Regulations, 2014 is a draft principal supply code for Gujarat. It would bind distribution licensees including deemed licensees, all consumers in Gujarat, persons exempt under Section 13 of the Electricity Act 2003, and cases of unauthorised supply or use (p7). It is made under Section 181(2)(x) read with Section 50 of the Electricity Act 2003 and Section 42(1)(b) of the Gujarat Electricity Industry (Reorganisation and Regulation) Act 2003 (p7). It comes into force on publication in the official Gazette; the Gazette date is not printed, but the draft is signed by the Secretary at Gandhinagar on 11/11/2014 (p7, p77).
Section 1 establishes the Supply Code Review Panel and its functions, the review and revision process, confidentiality, dispute referral to GERC, and interaction with other GERC regulations (p9–11). Section 2 defines core terms used across the Code (p12–18). Section 3 specifies the system of supply, voltage and frequency expectations, power-factor correction duties, parallel operation of consumer generating sets, and classification or reclassification of consumers into tariff categories approved by GERC (p19–21).
Section 4 is the longest and sets the end-to-end procedure for new connections and modifications: licensee obligation to supply and extend the system, conditions for grant, treatment of existing, sub-divided or reconstructed property, application forms and documents, processing and inspection timelines, deemed sanction for missed inspections, demand notes, temporary supply, transfer or change of name, conversion, shifting, reclassification, load enhancement and reduction, annual review of contract demand, and execution of agreement (p22–43). Section 5 governs apparatus on consumer premises — wiring, equipment, motors, agricultural pump sets, supply mains and licensee apparatus (p44–47).
Section 6 covers metering and billing: meter requirements, supply and installation, reading, testing, replacement, billing content and special billing situations, payment modes, delayed payment, instalments and recovery of arrears (p48–60). Section 7 sets procedures for theft of electricity and unauthorised use of electricity, including inspection, show-cause, assessment, compounding, voluntary declaration of tampered meters, appeals and consequences of default (p61–70). Section 8 covers temporary and permanent disconnection, disconnection on consumer request and reconnection (p71–73). Section 9 contains general provisions on failure or interruption, load shedding, harmonic limits, demand-side management, grievance redressal, service of notice, multiple violations, repeal and savings, interpretation and Commission powers (p74–77).
Annexures I–XII provide forms and formats for applications, test reports, theft assessment, meter complaints and testing, self-assessed bills, advance payment, permanent disconnection and disconnection intimations (p78–101). The Code states that annexed forms and formats are for guidance and licensees may amend them with prior Commission approval (p7). It repeals the 2005 Supply Code with savings (p76).
Read with this
The regulation
- Dated 21 Sep 2015Electricity Supply Code and Related Matters Regulations, 2015
Amendments and corrections
- Dated 22 Nov 2016Electricity Supply Code and Related Matters Regulations, 2015 — First Amendment, 2016
- Dated 16 Jan 2020Electricity Supply Code and Related Matters (Second Amendment) Regulations, 2020
- Dated 5 Dec 2023Electricity Supply Code and Related Matters, 2015 — Third Amendment Regulations, 2023
- Dated 1 Jan 2024Electricity Supply Code and Related Matters (Third Amendment) Regulations, 2023 — Corrigendum, 2024
- Dated 1 Jan 2024Electricity Supply Code and Related Matters (Third Amendment) Regulations, 2023 — Corrigendum
- Dated 23 Sep 2024Electricity Supply Code and Related Matters Regulations, 2015 — Fourth Amendment, 2024
Commencement notices and reasons
Consolidated copies, for reference (1)
Proposed changes (drafts with no final yet)
- Dated 17 Oct 2026Electricity Supply Code and Related Matters Regulations, 2015 — Fifth Amendment, 2026 — Draft
- Dated 17 Oct 2026Explanatory memorandum: Electricity Supply Code and Related Matters Regulations, 2015 — Fifth Amendment, 2026 — Explanatory Memorandum — Draft
Earlier drafts
- Dated 28 Sep 2016Electricity Supply Code and Related Matters (First Amendment) Regulations, 2016 — Draft
- Dated 28 Sep 2016Explanatory memorandum: Electricity Supply Code and Related Matters, 2015 — First Amendment, 2016 — Explanatory Memorandum — Draft
- Dated 2 Aug 2017Electricity Supply Code and Related Matters, 2015 — Second Amendment, 2017 — Draft
- Dated 24 Nov 2019Electricity Supply Code and Related Matters (Second Amendment) Regulations, 2019 — Draft
- Dated 24 Nov 2019Explanatory memorandum: Electricity Supply Code and Related Matters Regulations, 2015 — Second Amendment, 2019 — Explanatory Note — Draft
- Dated 19 Feb 2022Electricity Supply Code and Related Matters Regulations, 2015 — Third Amendment, 2022 — Draft
- Dated 19 Feb 2022Explanatory memorandum: Electricity Supply Code and Related Matters Regulations, 2015 — Draft Amendments — Explanatory Memorandum
- Dated 31 Aug 2024Electricity Supply Code and Related Matters, 2015 — Fourth Amendment, 2024 — Draft
- Dated 31 Aug 2024Explanatory memorandum: Electricity Supply Code and Related Matters, 2015 — Fourth Amendment, 2024 — Explanatory Note — Draft
6 more documents belong here and are not on Voltaic: 6 copies in another language.
Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.