KSERC · Kerala State Electricity Regulatory Commission
Kerala Electricity Supply Code (Removal of Difficulties) Order, 2025
Kerala Electricity Supply Code (Removal of Difficulties) Order 2025
OrderDated 6 Jan 2025No. 3401/Com.Ex./2023/KSERC dated 6 th January, 2025
Made under the Kerala Electricity Supply Code, 2014.
Summary
Summary written by software. Check the regulator's original before you rely on it.
KSERC's Removal of Difficulties Order, 2025 (No. 3401/Com.Ex./2023/KSERC, dated 6 January 2025) is a short, self-contained instrument that eases the route to electricity connection for individual buyers in stalled residential colonies and villa projects (p1).
The first four pages are recitals. They restate the regime being relaxed: Regulation 36(iii) of the Kerala Electricity Supply Code, 2014 makes the applicant — including a developer or builder of a colony with demand above one megawatt — bear the cost of extending or upgrading the distribution system undertaken exclusively for its connection (p1); Regulation 49, as amended in 2020 and by the Fifth Amendment Code 2024, splits the cost of modification/upgradation and internal-network construction between licensee and developer depending on whether the project's total load is above or at/below one megawatt (p1–2). Section 43(1) of the Electricity Act, 2003 requires supply within a month of application (p2–3). The Commission then records the difficulty: promoters abandon projects midway or miss RERA timelines, disputes pend before the Kerala Real Estate Regulatory Authority, and RERA cannot direct licensees under the Electricity Act; licensees therefore cannot recover capital expenditure or get the internal network built, leaving beneficiaries without supply (p3–4).
The operative part is two clauses (p4–6). Clause 1 gives the short title and brings the order into force from the date of the order. Clause 2, overriding Regulations 36 and 49, lets individual beneficiaries in such projects apply separately for service connections and requires the licensee to verify the application and estimate expenditure — separately for projects above one megawatt (extension/upgradation plus internal network) and those at or below it (internal network only), apportioned to each applicant by connected load. Beneficiaries pay their proportionate share; the balance is recovered from other beneficiaries as and when they apply. Clause 2 also lets the licensee carry the capital cost in GFA/NFA within its ARR & ERC and net it off as consumer contributions come in, and places maintenance of the internal distribution network on the licensee with cost recovery through ARR & ERC under the tariff regulations (p5–6).
Read with this
The regulation
- Dated 31 Jan 2014Kerala Electricity Supply Code, 2014
Amendments and corrections
- Dated 8 May 2015Kerala Electricity Supply Code, 2014 — Amendment, 2015
- Dated 11 Jan 2016Kerala Electricity Supply Code, 2014 — Amendment Code, 2016
- Dated 24 Jan 2017Kerala Electricity Supply (Amendment) Code, 2017
- Dated 22 Jan 2020Kerala Electricity Supply (Amendment) Code, 2020
- Dated 26 Jul 2024Kerala Electricity Supply Code, 2014 — Fifth Amendment, 2024
Commencement notices and reasons
Procedures and orders made under it
- Dated 23 Sep 2014Kerala Electricity Supply Code (Removal of Difficulties) Orders, 2014 — First to Fourth
- Dated 2 Jun 2015Kerala Electricity Supply Code (Removal of Difficulties) Fifth Order, 2015
- Dated 2 Jun 2015Kerala Electricity Supply Code (Removal of Difficulties) Fifth Order, 2015
- Dated 3 Jun 2015Kerala Electricity Supply Code (Removal of Difficulties) Sixth Order, 2015
- Dated 23 Jun 2015Kerala Electricity Supply Code (Removal of Difficulties) Sixth Order, 2015
- Dated 23 Jun 2015Kerala Electricity Supply Code — Sixth Removal of Difficulties Order, 2015
- Dated 11 Jul 2016Kerala Electricity Supply Code (Removal of Difficulties) Sixth Order, 2015 — validity extension to 30.09.2016
- Dated 26 Oct 2016Kerala Electricity Supply Code (Removal of Difficulties) Order, 2016
- Dated 26 Oct 2016Kerala Electricity Supply Code (Removal of Difficulties) Order, 2016
- Dated 20 Nov 2024Kerala Electricity Supply Code (Removal of Difficulties) Order, 2024
- Dated 20 Nov 2024Kerala Electricity Supply Code (Removal of Difficulties) Order, 2024
- Dated 6 Jan 2025Kerala Electricity Supply Code (Removal of Difficulties) Order, 2025
- Dated 9 Apr 2025Kerala Electricity Supply Code (Removal of Difficulties) (Second Order), 2025
- Dated 9 Apr 2025Kerala Electricity Supply Code (Removal of Difficulties) (Second Order), 2025
- Dated 9 Oct 2025Kerala Electricity Supply Code (Removal of Difficulties) (Third Order), 2025
- Dated 9 Oct 2025Kerala Electricity Supply Code (Removal of Difficulties) (Third Order), 2025
Consolidated copies, for reference (1)
- Dated 14 Oct 2025Kerala Electricity Supply Code, 2014 (as amended)
Other copies of these documents (2)
- Dated 22 Jan 2020Kerala Electricity Supply (Amendment) Code, 2020
- Dated 26 Jul 2024Kerala Electricity Supply Code, 2014 — Fifth Amendment Code, 2024
11 more documents belong here and are not on Voltaic: 11 copies in another language.
Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.