GERC · Gujarat Electricity Regulatory Commission
Green Energy Open Access Regulations, 2024 — First Amendment — Statement of Reasons
Gujarat Electricity Regulatory Commission (Terms and Conditions for Green Energy Open Access) (First Amendment) Regulations, 2024.
Statement of reasonsDated 23 Sep 2024
The commission's reasons for the Green Energy Open Access Regulations, 2024 or one of its amendments.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Gujarat Electricity Regulatory Commission's Statement of Reasons for the First Amendment to its Green Energy Open Access Regulations, 2024, recorded at Gandhinagar on 23/09/2024 (p4). The Principal Regulations — notified as Notification No. 08 of 2024 dated 21.02.2024 — had made the banking charge of Rs. 1.50 per unit effective only up to 30 September 2024, with charges from 1 October 2024 onwards to be fixed separately (p1).
Because the Commission's study to determine a banking-cost framework is still in progress, the amendment substitutes Regulation 1(4) and Regulation 17.6(viii) so the existing charge continues for a further six months, up to 31 March 2025 or an earlier date on which the Commission notifies charges by separate regulation (p2).
Section 2 records the consultation: a draft amendment notification dated 31.08.2024, public notices inviting suggestions and objections, written comments, and a public hearing held on 19.09.2024 (p2–3). Section 3 sets out stakeholder suggestions — banking charges in kind at 8% of banked energy and the lack of stated logic for the Rs. 1.50 rate; a marginal-cost power-purchase proposal to avoid socialising banking cost — and the Commission's reasoning for acknowledging but deferring them pending the ongoing cost study (p3). Suggestions on the base for levying banking charges, clarification of the 30% banked-energy quantum, and peak-hour drawal were held to be outside the scope of the draft and not considered at this stage (p4). The Commission directs publication of the amendment in the Official Gazette (p4). Annexure I lists stakeholders who filed written comments and Annexure II lists those present at the hearing (p5–6).
Read with this
The regulation
- Dated 20 Feb 2024Green Energy Open Access Regulations, 2024
Amendments and corrections
- Dated 23 Sep 2024Green Energy Open Access (First Amendment) Regulations, 2024
- Dated 28 Mar 2025Green Energy Open Access Regulations, 2024 — Second Amendment, 2025
- Dated 24 Sep 2025Green Energy Open Access Regulations, 2024 — Third Amendment, 2025
- Dated 30 Mar 2026Green Energy Open Access Regulations, 2024 — Fourth Amendment, 2026
- Dated 30 Jun 2026Green Energy Open Access Regulations, 2024 — Fifth Amendment, 2026
- Dated 19 Aug 2026Green Energy Open Access Regulations, 2024 — Sixth Amendment, 2026
- Dated 24 Sep 2026Green Energy Open Access (Sixth Amendment) Regulations, 2026 — Errata
Commencement notices and reasons
- Dated 20 Feb 2024Green Energy Open Access Regulations, 2024 — Statement of Reasons
- Dated 28 Mar 2025Green Energy Open Access Regulations, 2024 — Second Amendment, 2025 — Statement of Reasons
- Dated 25 Sep 2025Green Energy Open Access Regulations, 2024 — Third Amendment, 2025 — Statement of Reasons
- Dated 30 Mar 2026Green Energy Open Access Regulations, 2024 — Fourth Amendment, 2026 — Statement of Reasons
- Dated 30 Jun 2026Green Energy Open Access Regulations, 2024 — Fifth Amendment, 2026 — Statement of Reasons
- Dated 19 Aug 2026Green Energy Open Access Regulations, 2024 — Sixth Amendment, 2026 — Statement of Reasons
Procedures and orders made under it
Earlier drafts
- Dated 23 Jun 2023Green Energy Open Access Regulations, 2023 — Draft
- Dated 31 Aug 2024Green Energy Open Access Regulations, 2024 — First Amendment, 2024 — Draft
- Dated 31 Aug 2024Explanatory memorandum: Green Energy Open Access (First Amendment) Regulations, 2024 — Explanatory Note — Draft
- Dated 23 Jan 2025Green Energy Open Access Regulations, 2024 — Second Amendment, 2025 — Draft
- Dated 30 Aug 2025Green Energy Open Access Regulations, 2024 — Third Amendment, 2025 — Draft
- Dated 30 Aug 2025Explanatory memorandum: Terms and Conditions for Green Energy Open Access Regulations, 2024 — Third Amendment, 2025 — Explanatory Memorandum — Draft
- Dated 11 Mar 2026Terms & Conditions for Green Energy Open Access (Fourth Amendment) Regulations, 2026 — Draft
- Dated 11 Mar 2026Explanatory memorandum: Green Energy Open Access (Fourth Amendment) Regulations, 2026 — Explanatory Memorandum — Draft
- Dated 6 Jun 2026Green Energy Open Access (Fifth Amendment) Regulations, 2026 — Draft
- Dated 6 Jun 2026Explanatory memorandum: Green Energy Open Access Regulations, 2024 — Fifth Amendment, 2026 — Explanatory Memorandum — Draft
- Dated 20 Jun 2026Green Energy Open Access (Sixth Amendment) Regulations, 2026 — Draft
- Dated 20 Jun 2026File: Consultation Paper — Methodology for Determination of Banking Charges for RE Open Access Consumers under Green Energy Open Access Regulations, 2024
- Dated 20 Jun 2026Explanatory memorandum: Green Energy Open Access (Sixth Amendment) Regulations, 2026 — Explanatory Memorandum — Draft
5 more documents belong here and are not on Voltaic: 5 copies in another language.
Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.