GERC · Gujarat Electricity Regulatory Commission
Green Energy Open Access Regulations, 2024 — Statement of Reasons
Statement of Reasons — GERC (Terms and Conditions for Green Energy Open Access) Regulations, 2024
Statement of reasonsDated 20 Feb 2024
The commission's reasons for the Green Energy Open Access Regulations, 2024 or one of its amendments.
Summary
Summary written by software, from pages 1 to 40 of 332. Check the regulator's original before you rely on it.
The document is the Statement of Reasons (SoR) issued by the Gujarat Electricity Regulatory Commission for the Gujarat Electricity Regulatory Commission (Terms and Conditions for Green Energy Open Access) Regulations, 2024. Pages 1–2 set out the background: the Regulations are made under section 181 of the Electricity Act, 2003 read with sections 39, 40, 42, 61 and 86; they follow the Ministry of Power's Electricity (Promoting Renewable Energy through Green Energy Open Access) Rules, 2022 and amendments, the Central Nodal Agency/POSOCO procedure and the Forum of Regulators' model methodology for open access and banking charges. The Commission also records national renewable-energy and green-hydrogen targets (p1–2).
Page 3 describes consultation: the draft GERC Green Energy Open Access Regulations, 2023 was published on 23.06.2023, comments were invited up to 26.07.2023, a public hearing was held on 28.08.2023, and the Commission finalised the 2024 Regulations after considering stakeholder objections; Annexures I and II list commenters and hearing participants (p3).
Pages 4–40 are the core of the supplied portion: a regulation-by-regulation SoR. For each draft provision, it sets out stakeholder comments and the Commission's decision, often quoting the final or modified regulation text. It deals with Regulation 3 definitions—banking, captive generating plant, entity, existing open access consumer, green energy/renewable energy, green energy open access consumer, installation, month and State Nodal Agency (p4–15); Regulation 4 interpretation (p15–16); Regulation 5 scope (p16–17); Regulation 6 criteria for allowing GEOA, including planning-code compliance, network margins, metering and no-dues conditions (p17–19); Regulation 7 categories of long-term, medium-term and short-term open access (p19–23); Regulation 8 application procedure and the undertaking against multiple PPAs, with a modification allowing a drawee entity multiple PPAs within the granted quantum (p23–29); and Regulation 9 eligibility, captive-status verification, the 100 kW threshold for non-captive consumers and no load limit for captive use (p29–40). The portion ends mid-discussion of banking charges and scheduling.
Read with this
The regulation
- Dated 20 Feb 2024Green Energy Open Access Regulations, 2024
Amendments and corrections
- Dated 23 Sep 2024Green Energy Open Access (First Amendment) Regulations, 2024
- Dated 28 Mar 2025Green Energy Open Access Regulations, 2024 — Second Amendment, 2025
- Dated 24 Sep 2025Green Energy Open Access Regulations, 2024 — Third Amendment, 2025
- Dated 30 Mar 2026Green Energy Open Access Regulations, 2024 — Fourth Amendment, 2026
- Dated 30 Jun 2026Green Energy Open Access Regulations, 2024 — Fifth Amendment, 2026
- Dated 19 Aug 2026Green Energy Open Access Regulations, 2024 — Sixth Amendment, 2026
- Dated 24 Sep 2026Green Energy Open Access (Sixth Amendment) Regulations, 2026 — Errata
Commencement notices and reasons
- Dated 23 Sep 2024Green Energy Open Access Regulations, 2024 — First Amendment — Statement of Reasons
- Dated 28 Mar 2025Green Energy Open Access Regulations, 2024 — Second Amendment, 2025 — Statement of Reasons
- Dated 25 Sep 2025Green Energy Open Access Regulations, 2024 — Third Amendment, 2025 — Statement of Reasons
- Dated 30 Mar 2026Green Energy Open Access Regulations, 2024 — Fourth Amendment, 2026 — Statement of Reasons
- Dated 30 Jun 2026Green Energy Open Access Regulations, 2024 — Fifth Amendment, 2026 — Statement of Reasons
- Dated 19 Aug 2026Green Energy Open Access Regulations, 2024 — Sixth Amendment, 2026 — Statement of Reasons
Procedures and orders made under it
Earlier drafts
- Dated 23 Jun 2023Green Energy Open Access Regulations, 2023 — Draft
- Dated 31 Aug 2024Green Energy Open Access Regulations, 2024 — First Amendment, 2024 — Draft
- Dated 31 Aug 2024Explanatory memorandum: Green Energy Open Access (First Amendment) Regulations, 2024 — Explanatory Note — Draft
- Dated 23 Jan 2025Green Energy Open Access Regulations, 2024 — Second Amendment, 2025 — Draft
- Dated 30 Aug 2025Green Energy Open Access Regulations, 2024 — Third Amendment, 2025 — Draft
- Dated 30 Aug 2025Explanatory memorandum: Terms and Conditions for Green Energy Open Access Regulations, 2024 — Third Amendment, 2025 — Explanatory Memorandum — Draft
- Dated 11 Mar 2026Terms & Conditions for Green Energy Open Access (Fourth Amendment) Regulations, 2026 — Draft
- Dated 11 Mar 2026Explanatory memorandum: Green Energy Open Access (Fourth Amendment) Regulations, 2026 — Explanatory Memorandum — Draft
- Dated 6 Jun 2026Green Energy Open Access (Fifth Amendment) Regulations, 2026 — Draft
- Dated 6 Jun 2026Explanatory memorandum: Green Energy Open Access Regulations, 2024 — Fifth Amendment, 2026 — Explanatory Memorandum — Draft
- Dated 20 Jun 2026Green Energy Open Access (Sixth Amendment) Regulations, 2026 — Draft
- Dated 20 Jun 2026File: Consultation Paper — Methodology for Determination of Banking Charges for RE Open Access Consumers under Green Energy Open Access Regulations, 2024
- Dated 20 Jun 2026Explanatory memorandum: Green Energy Open Access (Sixth Amendment) Regulations, 2026 — Explanatory Memorandum — Draft
5 more documents belong here and are not on Voltaic: 5 copies in another language.
Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.