Skip to content

CERC · Central Electricity Regulatory Commission

Explanatory Memorandum — Draft Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) and Power System Development Fund (First Amendment) Regulations, 2015

Explanatory Memorandum to Draft CERC (Sharing of inter-State Transmission Charges and Losses)(Fourth Amendment) Regulations, 2015 and Draft Central Electricity Regulatory Commission (Power System Development Fund) (First Amendment) Regulations, 2015

Explanatory memorandum to a draftReleased with the notice dated 27 May 2015

Explanatory memorandum to the Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

Explanatory Memorandum accompanying two draft CERC amendment regulations: the Fourth Amendment to the CERC (Sharing of inter-State Transmission Charges and Losses) Regulations, 2010, and the First Amendment to the CERC (Power System Development Fund) Regulations, 2014. It explains why the amendments are needed and what they are intended to do.

It begins by reciting the Ministry of Power scheme for utilisation of gas-based power generation capacity, sanctioned by Office Memorandum No. 4/2/2015-Th.I dated 27 March 2015 (p1). The memorandum describes the scheme's scope — supply of imported spot RLNG ('e-bid RLNG') to stranded gas-based plants and plants receiving domestic gas through reverse e-bidding — as well as its funding, eligible utilities and stakeholder contributions (p1). It then reproduces paras 5(x) and 5(xi) of the scheme, which provide for transmission-charge and loss exemption for stranded gas-based projects on the lines of solar power, and PSDF support through a transparent reverse e-bidding process (p2).

The operational part explains the two regulatory changes. For the Sharing Regulations, it proposes adding clauses to Regulation 7(1) so that no ISTS transmission charges or losses are payable on incremental gas-based generation from e-bid RLNG for FY 2015-16 and FY 2016-17 (p2–3). The memorandum states that this waiver is limited to the two-year period because the scheme itself is for FY 2015-16 and FY 2016-17 and is to be reviewed thereafter (p3). For the PSDF Regulations, it proposes a new sub-regulation 3A allowing any Central Government scheme for power-system development that requires PSDF support to be eligible for assistance (p3).

Finally, the memorandum narrows both the transmission waiver and PSDF support to actual e-bid RLNG generation that is above the plant's base PLF, achieved during April–January 2014-15, and up to the target PLF defined by the Empowered Pool Management Committee (p3). It notes that for plants receiving domestic gas, support is similarly limited to actual generation from e-bid RLNG above base PLF up to target PLF (p3).

Standard name
Sharing of Inter-State Transmission Charges and Losses
Primary topics
Transmission tariff, Power System Development Fund (PSDF)

Read with this

Other copies of these documents (7)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document