CERC · Central Electricity Regulatory Commission
Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Second Amendment, 2012 — Statement of Reasons
The Central Electricity Regulatory Commission (Sharing of inter-State Transmission Charges and Losses) (Second Amendment) Regulations, 2012.
Statement of reasonsDated 2 May 2012
Replaced by Sharing of Inter-State Transmission Charges and Losses Regulations, 2020
See that regulation for the date it took effect and for anything it keeps in force.
The commission's reasons for the Sharing of Inter State Transmission Charges and Losses Regulations, 2010 or one of its amendments.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken under the repealed regulations shall be deemed to have been done or taken under these regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is CERC's Statement of Reasons dated 2 May 2012 for the Second Amendment to the 2010 Sharing Regulations, which govern inter-State transmission charges and losses (p1). It records the draft amendment posted on 14 February 2012, written comments from 19 stakeholders, and the 13 March 2012 public hearing (p1–2, p25–26). The SoR then takes each proposed change and states the Commission's final decision.
On approved injection and withdrawal, the Commission excludes overload capability from LTA calculations and adopts the LTA figure where the CTU has granted LTA, otherwise installed capacity minus auxiliary consumption; it rejects retrospective application from 1 July 2011 (p2–7). It amends the Implementing Agency definition, drops the proposed 'natural inter-State transmission line' definition in favour of 'inter-State transmission line connecting two States', and updates the Yearly Transmission Charge definition (p7–9).
It continues slab rates for injection and demand PoC and for transmission losses during the transition, with rationalisation to be reviewed in 2014-15, and links load-flow studies to YTC revisions (p9–14, p19–20). It directs zoning, including separate NER State zones, treats 400 kV ISGS as separate zones, deletes the old 1500 MW/500 MW pooling thresholds, and addresses high PoC injection for low-LTA stations (p14–18). It allocates Talcher-Kolar HVDC YTC to Southern Region DICs and uses the Talcher-I injection rate for Odisha's Talcher-II share (p20–21). It modifies the Annexure computation table (p22–24) and lists stakeholders (p25–26).
Read with this
The regulation
Amendments and corrections
- Dated 24 Nov 2011Sharing of inter-State Transmission Charges and Losses, 2010 — First Amendment, 2011
- Dated 28 Mar 2012Sharing of inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012
- Dated 1 Apr 2015Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment, 2015
- Dated 1 Apr 2015Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment, 2015
- Dated 3 Jul 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015
- Dated 14 Dec 2017Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017
- Dated 27 Mar 2019Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2019
Commencement notices and reasons
- Dated 11 Jun 2010Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Statement of Reasons
- Dated 21 Nov 2011Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — First Amendment, 2011 — Statement of Reasons
- Dated 18 Sep 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 — Statement of Reasons
- Dated 26 Oct 2015Sharing of Inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2015 — Statement of Reasons
- Dated 15 Dec 2017Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — 5th Amendment, 2017 — Statement of Reasons
- Dated 23 Apr 2019Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Statement of Reasons
- Date not statedComments on Draft Amendment to Sharing of Inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2014
- Date not statedAppendix-II — Stakeholder comments on draft Third Amendment to the Sharing of Inter-State Transmission Charges and Losses Regulations, 2014
Procedures and orders made under it
Other copies of these documents (7)
- Dated 30 Dec 2010Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Commencement Notification
- Dated 30 Dec 2010Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Commencement Notification
- Dated 24 Nov 2011Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — First Amendment, 2011
- Dated 28 Mar 2012Sharing of Inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012
- Dated 3 Jul 2015Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Fourth Amendment, 2015
- Dated 14 Dec 2017Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017
- Dated 27 Mar 2019Sharing of inter-State Transmission Charges and Losses (Sixth Amendment) Regulations, 2019
Earlier drafts
- Dated 7 Feb 2014Sharing of Inter-State Transmission Charges and Losses, 2010 — Third Amendment, 2014 — Draft
- Released with the notice dated 7 Feb 2014Explanatory memorandum: Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment — Explanatory Memorandum
- Dated 7 Feb 2014Public notice: Draft Sharing of inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2014 — Public Notice
- Dated 24 Feb 2014Notice extending the date for comments: Public Notice — Extension of time for comments on draft Sharing of Inter-state Transmission Charges and Losses (Third Amendment) Regulations, 2014
- Dated 27 May 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 — Draft
- Released with the notice dated 27 May 2015Explanatory memorandum: Explanatory Memorandum — Draft Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) and Power System Development Fund (First Amendment) Regulations, 2015
- Dated 27 May 2015Public notice: Public Notice — Draft Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 and Draft Power System Development Fund (First Amendment) Regulations, 2015
- Dated 28 Oct 2016Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Fifth Amendment, 2016 — Draft
- Released with the draft dated 28 Oct 2016Explanatory memorandum: Explanatory Memorandum to draft Connectivity, LTA and MTOA (Sixth Amendment) Regulations, 2015 and Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2016 — Draft
- Dated 16 Nov 2016Notice extending the date for comments: Public Notice — Extension of comment deadline on draft Connectivity, LTA and MTOA (Sixth Amendment) and Sharing of Inter-State Transmission Charges & Losses (Fifth Amendment) Regulations, 2016
- Dated 27 Apr 2018Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft
- Dated 27 Apr 2018Public notice: Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft — Public Notice
- Released with the notice dated 27 Apr 2018Explanatory memorandum: Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment — Explanatory Memorandum — Draft
2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.