Skip to content

CERC · Central Electricity Regulatory Commission

Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Second Amendment, 2012 — Statement of Reasons

The Central Electricity Regulatory Commission (Sharing of inter-State Transmission Charges and Losses) (Second Amendment) Regulations, 2012.

Statement of reasonsDated 2 May 2012

Replaced by Sharing of Inter-State Transmission Charges and Losses Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Sharing of Inter State Transmission Charges and Losses Regulations, 2010 or one of its amendments.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken under the repealed regulations shall be deemed to have been done or taken under these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's Statement of Reasons dated 2 May 2012 for the Second Amendment to the 2010 Sharing Regulations, which govern inter-State transmission charges and losses (p1). It records the draft amendment posted on 14 February 2012, written comments from 19 stakeholders, and the 13 March 2012 public hearing (p1–2, p25–26). The SoR then takes each proposed change and states the Commission's final decision.

On approved injection and withdrawal, the Commission excludes overload capability from LTA calculations and adopts the LTA figure where the CTU has granted LTA, otherwise installed capacity minus auxiliary consumption; it rejects retrospective application from 1 July 2011 (p2–7). It amends the Implementing Agency definition, drops the proposed 'natural inter-State transmission line' definition in favour of 'inter-State transmission line connecting two States', and updates the Yearly Transmission Charge definition (p7–9).

It continues slab rates for injection and demand PoC and for transmission losses during the transition, with rationalisation to be reviewed in 2014-15, and links load-flow studies to YTC revisions (p9–14, p19–20). It directs zoning, including separate NER State zones, treats 400 kV ISGS as separate zones, deletes the old 1500 MW/500 MW pooling thresholds, and addresses high PoC injection for low-LTA stations (p14–18). It allocates Talcher-Kolar HVDC YTC to Southern Region DICs and uses the Talcher-I injection rate for Odisha's Talcher-II share (p20–21). It modifies the Annexure computation table (p22–24) and lists stakeholders (p25–26).

Standard name
Sharing of Inter-State Transmission Charges and Losses
Primary topics
Transmission tariff, Losses and loss reduction

Read with this

Other copies of these documents (7)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.