Skip to content

CERC · Central Electricity Regulatory Commission

Sharing of Inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012

Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) (Second Amendment) Regulations, 2012

Amendment · Gazette copyDated 28 Mar 2012Published in the Gazette 29 Mar 2012No. L-1/44/2010-CERC. dated 28th March, 2012

Replaced by Sharing of Inter-State Transmission Charges and Losses Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Sharing of inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken under the repealed regulations shall be deemed to have been done or taken under these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Second Amendment to CERC's 2010 framework for sharing inter-State transmission charges and losses, made under Section 178 of the Electricity Act, 2003 and coming into force on publication in the Gazette on 29 March 2012 (p1, p6). It is a short, dense instrument that alters definitions, computation rules and the Annexure rather than restating the principal regime.

Regulation 2 (p6–7) inserts provisos on how 'approved injection' and 'approved withdrawal' under long-term access are computed — overload capability is excluded, and LTA or installed capacity net of auxiliary consumption is used — and rewrites the definitions of Implementing Agency and Yearly Transmission Charge.

Regulation 3 (p7–9) reworks Regulation 7: the timing of YTC revision, load flow studies on revision, the zonal structure for point-of-connection rates (demand zones follow State boundaries; 400 kV inter-State generating stations become separate zones; one para is deleted), and slabs for injection and demand PoC charges and for transmission losses. Regulation 4 (p9) fixes the RPCs' obligations to issue Regional Transmission Accounts and Regional Transmission Deviation Accounts. Regulation 5 (p10) and parts of Regulation 6 replace 'charge' with 'rate'.

Regulation 6 (p10–11) amends the Annexure: a new paragraph for Yearly Transmission Charges, a revised step allocating Talcher–Kolar HVDC cost to Southern Region customers, and a modified zone-computation table (p11). A closing note records the principal regulations' and first amendment's Gazette details (p11).

Standard name
Sharing of Inter-State Transmission Charges and Losses
Primary topics
Transmission tariff, Losses and loss reduction, Energy accounting and settlement

Read with this

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document