Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Statement of Reasons

Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010

Statement of reasonsDated 11 Jun 2010No. L-1/44/2010/CERC dated 11th June 2010

Replaced by Sharing of Inter-State Transmission Charges and Losses Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Sharing of Inter State Transmission Charges and Losses Regulations, 2010 or one of its amendments.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken under the repealed regulations shall be deemed to have been done or taken under these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software, from pages 1 to 36 of 43. Check the regulator's original before you rely on it.

This is the Central Electricity Regulatory Commission's Statement of Reasons for the CERC (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010, dated 11 June 2010 (p1). It is not the regulation text; it records why the Commission adopted a Point of Connection (PoC) framework for sharing inter-state transmission charges and losses. Pages 1–6 set out the statutory and policy mandate: Section 61 of the Electricity Act, the National Electricity Policy's call for a national transmission tariff framework sensitive to distance, direction and flow, and the Tariff Policy's loss-charging principle (p1–3). The Commission describes its consultation process and the methodology changes made after public hearings and workshops (p3). It also states that Yearly Transmission Charges remain determined under the Tariff Regulations in force (p6).

Section 2 begins the stakeholder-comment analysis (p6). Section 3.1 (pp6–18) deals with preliminary objections: why the Commission chose a Hybrid Method over pure Average Participation, how transparency and simplicity were treated, whether the charges are distance- and direction-sensitive, whether they provide siting signals, and why a transition mechanism is needed. Section 3.2 (pp18–20) records accepted changes to definitions, including renaming Annual Transmission Charge to Yearly Transmission Charge and revising Approved Withdrawal/Injection and Uniform Charge/Loss definitions. Section 3.3 (pp21–36) is the core: data submission, use of the Hybrid Method, the split between hybrid-method zonal charges and a uniform charge sharing component, network truncation, treatment of embedded and 220 kV assets, solar concessions, loss allocation factors, substation charge allocation, billing and deviation charges. Section 3.4 on zoning begins only at p36. Attachment-I (methodology/truncation) and Annexure-I (stakeholder list) are referenced.

Standard name
Sharing of Inter-State Transmission Charges and Losses
Primary topics
Transmission tariff, Losses and loss reduction, Open access

Read with this

Other copies of these documents (7)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗