CERC · Central Electricity Regulatory Commission

Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017

Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) (Fifth Amendment) Regulations, 2017

AmendmentDated 14 Dec 2017No.L-1/44/2010-CERC dated 14 th December, 2017

Replaced by Sharing of Inter-State Transmission Charges and Losses Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Sharing of Inter State Transmission Charges and Losses Regulations, 2010.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken under the repealed regulations shall be deemed to have been done or taken under these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Fifth Amendment to CERC's Sharing of Inter-State Transmission Charges and Losses Regulations, 2010, notified on 14 December 2017 (p1). It does two things: it creates a full waiver of ISTS transmission charges and losses for qualifying new solar and wind capacity, and it reworks the billing mechanics for designated ISTS customers (DICs) — start-up and infirm power, default PoC billing, and offsets between short/medium-term open access and long-term access.

New Regulation 7(1)(y) waives transmission charges and losses for solar capacity awarded through competitive bidding, declared under commercial operation between 1.7.2017 and 31.12.2019, and selling to distribution companies under PPAs for their RPO compliance; the waiver runs 25 years from commercial operation (p1). Clause 7(1)(z) does the same for wind capacity with a COD window of 30.9.2016 to 31.3.2019 (p2). These two sub-clauses are expressly backdated: they take effect from 1.7.2017 and 30.9.2016 respectively, while everything else commences on Gazette publication (p1).

Regulation 8 changes make a generating station drawing start-up power or injecting infirm power before LTA liable for withdrawal/injection charges, with the amounts reimbursed to DICs in proportion to their billing, and add a default rule billing a DIC with LTA at the target region's average PoC rate where the quarterly PoC rate has not been determined (p2). Regulation 11 changes substitute the second proviso to Clause (5) on medium-term open access adjustment against LTA, replace Clause (6) so that the third part of the transmission bill carries FERV, incentive, asset-rescheduling and arrears adjustments recovered from DICs in proportion to average approved injection/withdrawal charges, and replace the provisos to Clause (9) with a new Clause (10) governing STOA offsets — including quantity limits, the exclusion of intra-State embedded entities, treatment of collective transactions, and the carve-out for trading licensees with a generator portfolio (p2–4).

The closing Note lists the Principal Regulations and the four earlier amendments (p4).

Standard name
Sharing of Inter-State Transmission Charges and Losses
Primary topics
Transmission tariff, Open access

Read with this

Other copies of these documents (7)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page