Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment — Explanatory Memorandum — Draft

Explanatory Memorandum Draft 6 th Amendment to Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges & Losses)Regulations,2010

Explanatory memorandum to a draftReleased with the notice dated 27 Apr 2018

Explanatory memorandum to the Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The memorandum supports a draft Sixth Amendment to the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010. It changes no charge by itself: it explains why the Commission proposes to rewrite the waiver of inter-State transmission charges and losses available to solar and wind generation, and reproduces the exact wording proposed for Regulation 7 (p1, pp3–4).

Pages 1–3 lay out the policy chain behind the proposal. It opens with para 6.4(6) of the Tariff Policy notified by the Ministry of Power on 28.1.2016, which contemplates a Central Government-notified period during which no inter-State transmission charges and losses are levied on electricity from solar and wind sold through ISTS. It then reproduces, in sequence, the Ministry's notification of 30.9.2016 (commissioning cut-offs, a 25-year waiver from commissioning, restriction to PPAs with distribution companies for RPO compliance, and competitive-bidding award), its order of 14.6.2017 extending the solar cut-off, the Commission's own Fifth Amendment notification dated 14.12.2017 and the solar and wind commissioning windows that resulted, and finally the Ministry's order of 13.2.2018, which superseded the two earlier Ministry orders, extended the waiver to projects commissioned up to 31.3.2022, opened it to PPAs with all entities including distribution companies, and was to apply prospectively from its date of issue (p1–3).

The operative proposal (para 6, pp3–4) inserts a new sub-clause (aa) to Regulation 7(1) giving a 25-year waiver from commercial operation for competitively bid solar and wind capacity declared under commercial operation between 13.02.2018 and 31.3.2022, where PPAs exist with all entities including distribution companies for RPO compliance. It then substitutes dates in sub-clauses (y) and (z) of the same regulation, closing the earlier solar and wind windows immediately before the new clause begins.

Standard name
Sharing of Inter-State Transmission Charges and Losses
Primary topics
Transmission tariff

Read with this

Other copies of these documents (7)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document