CERC · Central Electricity Regulatory Commission
Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment — Explanatory Memorandum — Draft
Explanatory Memorandum Draft 6 th Amendment to Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges & Losses)Regulations,2010
Explanatory memorandum to a draftReleased with the notice dated 27 Apr 2018
Draft
The draft has since been finalised as the Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2019.
Explanatory memorandum to the Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The memorandum supports a draft Sixth Amendment to the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010. It changes no charge by itself: it explains why the Commission proposes to rewrite the waiver of inter-State transmission charges and losses available to solar and wind generation, and reproduces the exact wording proposed for Regulation 7 (p1, pp3–4).
Pages 1–3 lay out the policy chain behind the proposal. It opens with para 6.4(6) of the Tariff Policy notified by the Ministry of Power on 28.1.2016, which contemplates a Central Government-notified period during which no inter-State transmission charges and losses are levied on electricity from solar and wind sold through ISTS. It then reproduces, in sequence, the Ministry's notification of 30.9.2016 (commissioning cut-offs, a 25-year waiver from commissioning, restriction to PPAs with distribution companies for RPO compliance, and competitive-bidding award), its order of 14.6.2017 extending the solar cut-off, the Commission's own Fifth Amendment notification dated 14.12.2017 and the solar and wind commissioning windows that resulted, and finally the Ministry's order of 13.2.2018, which superseded the two earlier Ministry orders, extended the waiver to projects commissioned up to 31.3.2022, opened it to PPAs with all entities including distribution companies, and was to apply prospectively from its date of issue (p1–3).
The operative proposal (para 6, pp3–4) inserts a new sub-clause (aa) to Regulation 7(1) giving a 25-year waiver from commercial operation for competitively bid solar and wind capacity declared under commercial operation between 13.02.2018 and 31.3.2022, where PPAs exist with all entities including distribution companies for RPO compliance. It then substitutes dates in sub-clauses (y) and (z) of the same regulation, closing the earlier solar and wind windows immediately before the new clause begins.
Read with this
The regulation
Amendments and corrections
- Dated 24 Nov 2011Sharing of inter-State Transmission Charges and Losses, 2010 — First Amendment, 2011
- Dated 28 Mar 2012Sharing of inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012
- Dated 1 Apr 2015Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment, 2015
- Dated 1 Apr 2015Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment, 2015
- Dated 3 Jul 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015
- Dated 14 Dec 2017Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017
- Dated 27 Mar 2019Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2019
Commencement notices and reasons
- Dated 11 Jun 2010Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Statement of Reasons
- Dated 21 Nov 2011Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — First Amendment, 2011 — Statement of Reasons
- Dated 2 May 2012Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Second Amendment, 2012 — Statement of Reasons
- Dated 18 Sep 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 — Statement of Reasons
- Dated 26 Oct 2015Sharing of Inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2015 — Statement of Reasons
- Dated 15 Dec 2017Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — 5th Amendment, 2017 — Statement of Reasons
- Dated 23 Apr 2019Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Statement of Reasons
- Date not statedComments on Draft Amendment to Sharing of Inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2014
- Date not statedAppendix-II — Stakeholder comments on draft Third Amendment to the Sharing of Inter-State Transmission Charges and Losses Regulations, 2014
Procedures and orders made under it
Other copies of these documents (7)
- Dated 30 Dec 2010Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Commencement Notification
- Dated 30 Dec 2010Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Commencement Notification
- Dated 24 Nov 2011Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — First Amendment, 2011
- Dated 28 Mar 2012Sharing of Inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012
- Dated 3 Jul 2015Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Fourth Amendment, 2015
- Dated 14 Dec 2017Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017
- Dated 27 Mar 2019Sharing of inter-State Transmission Charges and Losses (Sixth Amendment) Regulations, 2019
Earlier drafts
- Dated 7 Feb 2014Sharing of Inter-State Transmission Charges and Losses, 2010 — Third Amendment, 2014 — Draft
- Released with the notice dated 7 Feb 2014Explanatory memorandum: Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment — Explanatory Memorandum
- Dated 7 Feb 2014Public notice: Draft Sharing of inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2014 — Public Notice
- Dated 24 Feb 2014Notice extending the date for comments: Public Notice — Extension of time for comments on draft Sharing of Inter-state Transmission Charges and Losses (Third Amendment) Regulations, 2014
- Dated 27 May 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 — Draft
- Released with the notice dated 27 May 2015Explanatory memorandum: Explanatory Memorandum — Draft Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) and Power System Development Fund (First Amendment) Regulations, 2015
- Dated 27 May 2015Public notice: Public Notice — Draft Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 and Draft Power System Development Fund (First Amendment) Regulations, 2015
- Dated 28 Oct 2016Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Fifth Amendment, 2016 — Draft
- Released with the draft dated 28 Oct 2016Explanatory memorandum: Explanatory Memorandum to draft Connectivity, LTA and MTOA (Sixth Amendment) Regulations, 2015 and Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2016 — Draft
- Dated 16 Nov 2016Notice extending the date for comments: Public Notice — Extension of comment deadline on draft Connectivity, LTA and MTOA (Sixth Amendment) and Sharing of Inter-State Transmission Charges & Losses (Fifth Amendment) Regulations, 2016
- Dated 27 Apr 2018Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft
- Dated 27 Apr 2018Public notice: Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft — Public Notice
2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.