CERC · Central Electricity Regulatory Commission
Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment, 2015
Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) (Third Amendment) Regulations, 2015
AmendmentDated 1 Apr 2015In force from 1 May 2015No.L-1/44/2010-CERC dated 1st of April, 2015
Replaced by Sharing of Inter-State Transmission Charges and Losses Regulations, 2020
See that regulation for the date it took effect and for anything it keeps in force.
Amends the Sharing of Inter State Transmission Charges and Losses Regulations, 2010.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken under the repealed regulations shall be deemed to have been done or taken under these regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the CERC's Third Amendment to its 2010 regulations on sharing inter-State transmission charges and losses, notified on 1 April 2015 and brought into force on 1 May 2015 (p1). It is a substantial rewrite of definitions, charge-computation mechanics and billing, not a marginal correction.
Regulation 2 redefines the building blocks of the Point of Connection (PoC) system: Application Period, Approved Injection, Approved Withdrawal, Approved Additional Medium Term Withdrawal, Designated ISTS Customer, and new terms HVDC Charge, Merchant Power Plant, Reliability Support Charge and its sharing methodology, and Validation Committee; some existing sub-clauses are deleted (p1–4). Regulation 3 widens the applicability clause for generating stations, and Regulation 5(4) changes the unit in which charges are expressed (p4).
Regulation 7 is the core (p4–8): submission and vetting of forecast generation and demand data by DICs, validation by the Validation Committee against three years of historical data, a mis-declaration tolerance treated as gaming, preparation and convergence of the Basic Network load flow, slab-based PoC rates, application of the Hybrid Methodology, recovery of Yearly Transmission Charges through PoC, Reliability Support and HVDC charges, loss apportionment, and special treatment of 400 kV inter-State generators and merchant plants.
Regulation 8 makes a DIC liable for allocated charges when its approved injection or withdrawal does not materialise, including on LTA delay and part-commissioned transmission (p8–9). Regulation 11 prescribes a three-part bill — PoC, Reliability Support and HVDC charges; then additional MTOA; then over/under-recovery adjustment — with offset rules for MTOA and STOA (p10–13). Regulations 16 and 17 reset data-submission timelines and the Implementing Agency's publication duties (p13–14). Annexure-I amendments supply the detailed methodology for nodal data, load flow, HVDC cost sharing, slab computation, Reliability Support Charge rates and worked billing examples (p14–21). The closing Note records the Gazette publication dates of the principal regulations and the first two amendments (p21).
Read with this
The regulation
Amendments and corrections
- Dated 24 Nov 2011Sharing of inter-State Transmission Charges and Losses, 2010 — First Amendment, 2011
- Dated 28 Mar 2012Sharing of inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012
- Dated 1 Apr 2015Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment, 2015
- Dated 3 Jul 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015
- Dated 14 Dec 2017Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017
- Dated 27 Mar 2019Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2019
Commencement notices and reasons
- Dated 11 Jun 2010Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Statement of Reasons
- Dated 21 Nov 2011Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — First Amendment, 2011 — Statement of Reasons
- Dated 2 May 2012Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Second Amendment, 2012 — Statement of Reasons
- Dated 18 Sep 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 — Statement of Reasons
- Dated 26 Oct 2015Sharing of Inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2015 — Statement of Reasons
- Dated 15 Dec 2017Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — 5th Amendment, 2017 — Statement of Reasons
- Dated 23 Apr 2019Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Statement of Reasons
- Date not statedComments on Draft Amendment to Sharing of Inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2014
- Date not statedAppendix-II — Stakeholder comments on draft Third Amendment to the Sharing of Inter-State Transmission Charges and Losses Regulations, 2014
Procedures and orders made under it
Other copies of these documents (7)
- Dated 30 Dec 2010Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Commencement Notification
- Dated 30 Dec 2010Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Commencement Notification
- Dated 24 Nov 2011Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — First Amendment, 2011
- Dated 28 Mar 2012Sharing of Inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012
- Dated 3 Jul 2015Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Fourth Amendment, 2015
- Dated 14 Dec 2017Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017
- Dated 27 Mar 2019Sharing of inter-State Transmission Charges and Losses (Sixth Amendment) Regulations, 2019
Earlier drafts
- Dated 7 Feb 2014Sharing of Inter-State Transmission Charges and Losses, 2010 — Third Amendment, 2014 — Draft
- Released with the notice dated 7 Feb 2014Explanatory memorandum: Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment — Explanatory Memorandum
- Dated 7 Feb 2014Public notice: Draft Sharing of inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2014 — Public Notice
- Dated 24 Feb 2014Notice extending the date for comments: Public Notice — Extension of time for comments on draft Sharing of Inter-state Transmission Charges and Losses (Third Amendment) Regulations, 2014
- Dated 27 May 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 — Draft
- Released with the notice dated 27 May 2015Explanatory memorandum: Explanatory Memorandum — Draft Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) and Power System Development Fund (First Amendment) Regulations, 2015
- Dated 27 May 2015Public notice: Public Notice — Draft Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 and Draft Power System Development Fund (First Amendment) Regulations, 2015
- Dated 28 Oct 2016Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Fifth Amendment, 2016 — Draft
- Released with the draft dated 28 Oct 2016Explanatory memorandum: Explanatory Memorandum to draft Connectivity, LTA and MTOA (Sixth Amendment) Regulations, 2015 and Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2016 — Draft
- Dated 16 Nov 2016Notice extending the date for comments: Public Notice — Extension of comment deadline on draft Connectivity, LTA and MTOA (Sixth Amendment) and Sharing of Inter-State Transmission Charges & Losses (Fifth Amendment) Regulations, 2016
- Dated 27 Apr 2018Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft
- Dated 27 Apr 2018Public notice: Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft — Public Notice
- Released with the notice dated 27 Apr 2018Explanatory memorandum: Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment — Explanatory Memorandum — Draft
2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.