CERC · Central Electricity Regulatory Commission
Explanatory Memorandum to draft Connectivity, LTA and MTOA (Sixth Amendment) Regulations, 2015 and Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2016 — Draft
Explanatory Memorandum to draft Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) (Sixth Amendment) Regulations, 2015 and draft Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, Fifth Amendment 2016.
Explanatory memorandum to a draftReleased with the draft dated 28 Oct 2016
Draft
The draft has since been finalised as the Inter-State Connectivity, LTA and MTOA Regulations, 2009 — Sixth Amendment, 2017.
Explanatory memorandum to the Grant of Connectivity, Long-term Access and Medium-term Open Access (Sixth Amendment) Regulations, 2016 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is CERC's explanatory memorandum setting out the reasoning for two packages of draft amendments and inviting comments from stakeholders. Part A (p1-2) gives the market background: falling short-term prices, rising short-term volumes, generators relinquishing long-term access while still evacuating power under short-term and medium-term open access, and CTU's warning that transmission planning, which is driven by long-term access, will under-build capacity and cause congestion.
Part B (p2-16) proposes amendments to the 2009 Connectivity, Long-term Access and Medium-term Open Access Regulations. It would shorten the minimum long-term access period to align with the definition of long-term procurement in the 2005 bidding guidelines; insert a clause obliging an LTA customer with a target region to notify its PPA, with scheduling, last-mile link timelines, a one-month processing deadline on CTU and curtailment of MTOA/STOA on that corridor; revise the MTOA definition and the window for its start date; drop 'transmission system under execution' from the test for granting MTOA while leaving existing grants undisturbed; replace the dedicated transmission line regulation so the generator develops, owns and operates the line to the pooling station, with a cap on its length and charging rules for lines already built by CTU; add a provision on underutilisation of LTA/MTOA; and insert power to relax and power to remove difficulties.
Part C (p16-30) proposes amendments to the Sharing of Inter-State Transmission Charges and Losses Regulations: a reliability support charge on connectivity quantum not covered by LTA/MTOA; higher transmission charges for MTOA and STOA customers who have not sought LTA, with the surplus refunded to DICs; adoption of the MoP waiver of ISTS charges and losses for wind projects awarded by competitive bidding and commissioned by the stated cut-off, with no change proposed for solar; moving the third part of the transmission bill onto a quarterly cycle; clarifying the offset given to LTA customers who also pay MTOA/STOA charges; and a rule for billing generators at the target-region average PoC rate where their rate has not been notified.
Read with this
Read with this: Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009
The regulation
Amendments and corrections
- Dated 3 Sep 2010Inter-State Connectivity, Long-term Access and Medium-term Open Access Regulations, 2009 — Amendment, 2010
- Dated 21 Mar 2012Connectivity, LTA and MTOA in inter-State Transmission Regulations, 2009 — Second Amendment, 2012
- Dated 26 Mar 2013Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013
- Dated 12 Aug 2014Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Fourth Amendment, 2014
- Dated 15 May 2015Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2015
- Dated 17 Feb 2017Inter-State Connectivity, LTA and MTOA Regulations, 2009 — Sixth Amendment, 2017
- Dated 17 Feb 2017Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Sixth Amendment, 2017
- Dated 9 Jan 2019Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Seventh Amendment) Regulations, 2019
- Dated 5 Aug 2019Corrigendum 2 to Notification dated 9 January 2019
Commencement notices and reasons
- Dated 7 Aug 2009Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Order directing gazette publication
- Dated 30 Oct 2009Connectivity, Long-Term Access and Medium-Term Open Access to the Inter-State Transmission Regulations, 2009 — Statement of Reasons
- Dated 21 Mar 2012Connectivity, LTA and MTOA Regulations, 2009 — Second Amendment, 2012 — Statement of Reasons
- Dated 6 May 2015Connectivity Regulations, 2009 — Fourth Amendment, 2014 — Statement of Reasons
- Dated 15 May 2015Connectivity, LTA and MTOA Regulations, 2009 and Regulatory Approval Regulations, 2010 — Fifth Amendment, 2015 — Statement of Reasons
- Dated 28 Mar 2018Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Sixth Amendment) Regulations, 2017 — Statement of Reasons
- Dated 9 Jan 2019Connectivity Regulations, 2018 — Seventh Amendment — Statement of Reasons
- Date not statedConnectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Statement of Reasons
Procedures and orders made under it
- Dated 31 Dec 2009Procedure for Making Application for Grant of Connectivity in ISTS, 2009
- Dated 15 May 2018Approval of Detailed Procedure for Grant of Connectivity to RE Projects to ISTS, 2018 — Order
- Dated 20 Feb 2021Revised Procedure for Grant of Connectivity to Renewable Projects to the Inter-State Transmission System — Order, 2021
- Date not statedDetailed Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Date not statedRevised Procedure for Grant of Connectivity to Projects based on Renewable Sources to ISTS
Other copies of these documents (7)
- Dated 7 Jul 2009Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009
- Dated 3 Sep 2010Connectivity, Long-term Access and Medium-term Open Access in Inter-State Transmission Regulations, 2009 — Amendment, 2010
- Dated 21 Mar 2012Grant of Connectivity, Long-term Access and Medium-term Open Access (Second Amendment) Regulations, 2012
- Dated 26 Mar 2013Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Third Amendment) Regulations, 2013
- Dated 12 Aug 2014Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2014
- Dated 15 May 2015Connectivity, LTA and MTOA (Fifth Amendment) Regulations, 2015
- Dated 9 Jan 2019Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission (Seventh Amendment) Regulations, 2019
Proposed changes (drafts with no final yet)
- Dated 16 Apr 2015Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Fourth Amendment, 2015 — Draft
- Released with the notice dated 16 Apr 2015Explanatory memorandum: Explanatory Memorandum — Connectivity/LTA/MTOA (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015
- Dated 16 Apr 2015Public notice: Public Notice — Draft Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) and CTU Regulatory Approval (First Amendment) Regulations, 2015
- Released with the notice dated 11 Apr 2018Draft Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Dated 11 Apr 2018Public notice: Public Notice on Draft Procedure for Grant of Connectivity to Renewable Energy Projects, 2018
- Released with the notice dated 24 Jul 2020Detailed Procedure for Grant of Connectivity to Renewable Projects to ISTS
- Dated 24 Jul 2020Public notice: Draft Amendment to Detailed Procedure for Renewable Connectivity to Inter-State Transmission — Public Notice, 2020
Earlier drafts
- Dated 7 Jul 2009Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Consolidated
- Released with the draft dated 7 Jul 2009Explanatory memorandum: Connectivity, LTA and MTOA Seventh Amendment Regulations, 2018 — Explanatory Memorandum — Draft
- Dated 9 Aug 2018Public notice: Public Notice — Draft Connectivity, Long-term Access and Medium-term Open Access (Seventh Amendment) Regulations, 2018
- Dated 5 Sep 2018Notice extending the date for comments: Public Notice — Extension of comments deadline on Draft Connectivity, LTA and MTOA (Seventh Amendment) Regulations, 2018
- Dated 22 Feb 2013Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Draft
- Dated 22 Feb 2013Public notice: Connectivity, LTA and MTOA in inter-State Transmission (Third Amendment) Regulations, 2013 — Draft — Public Notice
- Released with the notice dated 22 Feb 2013Explanatory memorandum: Connectivity, LTA and MTOA (Third Amendment) Regulations, 2013 — Explanatory Memorandum — Draft
- Dated 18 Feb 2014Inter-State Transmission Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) Regulations, 2014 — Draft
- Released with the draft dated 18 Feb 2014File: Start-up Power for New Generating Stations Procedure, 2014
- Dated 20 Feb 2014Explanatory memorandum: Explanatory Memorandum to the Connectivity Regulations, 2009 Amendment, 2014
- Dated 24 Feb 2014Public notice: Connectivity, Long-term Access and Medium-term Open Access (Fourth Amendment) Regulations, 2014 — Draft
- Dated 28 Oct 2016Grant of Connectivity, Long-term Access and Medium-term Open Access (Sixth Amendment) Regulations, 2016 — Draft
- Dated 16 Nov 2016Notice extending the date for comments: Public Notice — Extension of comment deadline on draft Connectivity, LTA and MTOA (Sixth Amendment) and Sharing of Inter-State Transmission Charges & Losses (Fifth Amendment) Regulations, 2016
- Dated 9 Aug 2018Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission Regulations, 2009 — Seventh Amendment, 2018 — Draft
4 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft not held as English text and 1 draft or notice on a draft.
It is also read with: Sharing of Inter State Transmission Charges and Losses Regulations, 2010
Draft · Explanatory memorandum to the Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Fifth Amendment, 2016 — Draft. The draft has since been finalised as the Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017.
The regulation
Amendments and corrections
- Dated 24 Nov 2011Sharing of inter-State Transmission Charges and Losses, 2010 — First Amendment, 2011
- Dated 28 Mar 2012Sharing of inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012
- Dated 1 Apr 2015Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment, 2015
- Dated 1 Apr 2015Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment, 2015
- Dated 3 Jul 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015
- Dated 14 Dec 2017Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017
- Dated 27 Mar 2019Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2019
Commencement notices and reasons
- Dated 11 Jun 2010Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Statement of Reasons
- Dated 21 Nov 2011Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — First Amendment, 2011 — Statement of Reasons
- Dated 2 May 2012Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Second Amendment, 2012 — Statement of Reasons
- Dated 18 Sep 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 — Statement of Reasons
- Dated 26 Oct 2015Sharing of Inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2015 — Statement of Reasons
- Dated 15 Dec 2017Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — 5th Amendment, 2017 — Statement of Reasons
- Dated 23 Apr 2019Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Statement of Reasons
- Date not statedComments on Draft Amendment to Sharing of Inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2014
- Date not statedAppendix-II — Stakeholder comments on draft Third Amendment to the Sharing of Inter-State Transmission Charges and Losses Regulations, 2014
Procedures and orders made under it
Other copies of these documents (7)
- Dated 30 Dec 2010Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Commencement Notification
- Dated 30 Dec 2010Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Commencement Notification
- Dated 24 Nov 2011Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — First Amendment, 2011
- Dated 28 Mar 2012Sharing of Inter-State Transmission Charges and Losses (Second Amendment) Regulations, 2012
- Dated 3 Jul 2015Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Fourth Amendment, 2015
- Dated 14 Dec 2017Sharing of Inter-State Transmission Charges and Losses (Fifth Amendment) Regulations, 2017
- Dated 27 Mar 2019Sharing of inter-State Transmission Charges and Losses (Sixth Amendment) Regulations, 2019
Earlier drafts
- Dated 7 Feb 2014Sharing of Inter-State Transmission Charges and Losses, 2010 — Third Amendment, 2014 — Draft
- Released with the notice dated 7 Feb 2014Explanatory memorandum: Sharing of inter-State Transmission Charges and Losses Regulations, 2010 — Third Amendment — Explanatory Memorandum
- Dated 7 Feb 2014Public notice: Draft Sharing of inter-State Transmission Charges and Losses (Third Amendment) Regulations, 2014 — Public Notice
- Dated 24 Feb 2014Notice extending the date for comments: Public Notice — Extension of time for comments on draft Sharing of Inter-state Transmission Charges and Losses (Third Amendment) Regulations, 2014
- Dated 27 May 2015Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 — Draft
- Released with the notice dated 27 May 2015Explanatory memorandum: Explanatory Memorandum — Draft Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) and Power System Development Fund (First Amendment) Regulations, 2015
- Dated 27 May 2015Public notice: Public Notice — Draft Sharing of inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2015 and Draft Power System Development Fund (First Amendment) Regulations, 2015
- Dated 28 Oct 2016Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Fifth Amendment, 2016 — Draft
- Dated 16 Nov 2016Notice extending the date for comments: Public Notice — Extension of comment deadline on draft Connectivity, LTA and MTOA (Sixth Amendment) and Sharing of Inter-State Transmission Charges & Losses (Fifth Amendment) Regulations, 2016
- Dated 27 Apr 2018Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft
- Dated 27 Apr 2018Public notice: Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment, 2018 — Draft — Public Notice
- Released with the notice dated 27 Apr 2018Explanatory memorandum: Sharing of Inter State Transmission Charges and Losses Regulations, 2010 — Sixth Amendment — Explanatory Memorandum — Draft
2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.