Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — 5th Amendment, 2017 — Statement of Reasons

Central Electricity Regulatory Commission (Sharing of inter-State Transmission Charges and Losses) Regulations (5th Amendment), 2017

Statement of reasonsDated 15 Dec 2017File No. L-1/44/2010-CERC dated 15th December, 2017

Replaced by Sharing of Inter-State Transmission Charges and Losses Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Sharing of Inter State Transmission Charges and Losses Regulations, 2010 or one of its amendments.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken under the repealed regulations shall be deemed to have been done or taken under these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software, from pages 1 to 30 of 35. Check the regulator's original before you rely on it.

This is CERC's Statement of Reasons for the Fifth Amendment to the Sharing of Inter-State Transmission Charges and Losses Regulations. It records the consultation on the draft amendment notified on 28.10.2016, written comments from 49 stakeholders and a public hearing on 17.11.2016, then gives the Commission's analysis and decisions issue by issue (p1–2). The lists of participants are in Appendix-I and Appendix-II.

Two major proposals were dropped for the present. Section 2 proposed a Reliability Support Charge on connectivity quantum for DICs/generators, but after stakeholder objections and in view of the draft GNA Regulations, the Commission decided not to introduce it and may review later (p2–7). Section 6 proposed higher MTOA/STOA transmission charges, but this was also deferred pending finalisation of the draft GNA Regulations (p16–24).

Section 3 is the main substantive amendment. It adds waivers from ISTS transmission charges and losses for competitively bid solar and wind projects, with conditions on commercial operation dates and PPAs with distribution licensees for RPO compliance; the wind waiver is stated to be effective from 30.9.2016 (p7–13). It also directs beneficiaries to file details through affidavit to POSOCO (p11).

Sections 4, 5, 7, 8 and 9 amend billing and settlement mechanics. They cover reimbursement of start-up/infirm power charges to DICs in the following month (p13–14); billing DICs with LTA at an average PoC rate when no rate is determined for the quarter (p14–16); offset of MTOA quantum against LTA quantum, on quantum rather than rupee terms (p24–26); quarterly Bill-3 adjustments including arrears from revision orders (p26–28).

Standard name
Sharing of Inter-State Transmission Charges and Losses
Primary topics
Transmission tariff, Open access, Connectivity and GNA

Read with this

Other copies of these documents (7)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.