Sharing of Inter-State Transmission Charges and Losses Regulations, 2010 — First Amendment, 2011

Central Electricity Regulatory Commission (Sharing of inter-State Transmission Charges and Losses)(First Amendment) Regulations, 2011

Amendment · Gazette copyDated 24 Nov 2011Published in the Gazette 25 Nov 2011No. L-1/44/2010-CERC. dated New Delhi, the 24th November, 2011

Replaced by Sharing of Inter-State Transmission Charges and Losses Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Sharing of inter-State Transmission Charges and Losses, 2010 — First Amendment, 2011.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken under the repealed regulations shall be deemed to have been done or taken under these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's first amendment to the 2010 regulations that share inter-State transmission charges among grid users through the point-of-connection (PoC) mechanism. It was notified on 24 November 2011 (p8) and, under its own commencement clause, takes effect from Gazette publication — the Gazette issue is dated 25 November 2011 (p1, p8). The Principal Regulations were published on 16 June 2010, as the closing Note records (p15). Only the Gazette cover page and the amendment text (pp8–15) are present in the file.

Regulation 2 rewrites the definitions that drive the PoC billing cycle — Approved Injection and Approved Withdrawal, now tied to validation by the Implementing Agency, to representative blocks of months and peak/off-peak scenarios, and to long-term and medium-term access (pp8–9). Provisos treat the distribution company or a state-designated agency as the Designated ISTS Customer where ISTS charges were billed to them before the regulations took effect, and let states designate an agency afterwards (p9). A new 'Target Region' definition covers a region where a generator with long-term access intends to sell but beneficiaries are not yet identified (p9), and Yearly Transmission Charge is redefined to cover existing and new assets of transmission and deemed licensees as well as RPC-certified non-ISTS lines (pp9–10).

Regulation 3 restates who bears the charges, adding state agencies acting on behalf of distribution companies, generators and bulk customers (p10). Regulation 7 changes how overall charges are apportioned to nodes: YTC is split by voltage level and conductor configuration using CTU indicative cost levels approved by the Commission, with a fixed revision calendar (p10); an existing sub-clause is deleted and a proviso lets the Commission use a single average generation-and-demand scenario for 2011-12 PoC charges (p11).

Regulation 11 reworks billing: a first bill built on PoC charges, Approved Withdrawal and Approved Injection; a second part; and a deviation bill raised within three working days of the RPC's Regional Transmission Deviation Account, with reimbursement and offset rules for medium- and short-term open access, target regions and synchronously connected grids (pp11–14). One clause is deleted (p13).

Regulation 6 amends the Annexure: how YTC of ISTS, deemed ISTS and RPC-certified non-ISTS lines is adopted or approved; grandfathering of lines certified as on 15.06.2010; a load-flow test requiring more than 50% of a line's power to be inter-State, vetted by NLDC (pp14–15); and allocation of the charges of named HVDC back-to-back and bi-pole inter-regional links (p15).

Standard name
Sharing of Inter-State Transmission Charges and Losses
Primary topics
Transmission tariff, Open access

Read with this

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.