CERC · Central Electricity Regulatory Commission
Deviation Settlement Mechanism and Related Matters (Third Amendment) Regulations, 2015 — Explanatory Memorandum — Draft
Explanatory Memorandum Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (Third Amendment) Regulations, 2015
Explanatory memorandum to a draftReleased with the notice dated 23 Oct 2015
Draft
The draft has since been finalised as the Deviation Settlement Mechanism and related matters Regulations, 2014 — Third Amendment, 2016.
Explanatory memorandum to the Deviation Settlement Mechanism and Related Matters, Third Amendment Regulations, 2015 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is CERC's explanatory memorandum to the proposed Third Amendment to the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) Regulations, 2014. It is not the amendment text; it sets out why the Commission is proposing revised State DSM limits and what States must do to manage load-generation balance (p1, p12).
Pages 1–2 introduce the DSM Regulations 2014, the first and second amendments, and the grid-discipline objective. They report frequency improvement and note that some States still deviate heavily, despite the existing volume limits, and that States have blamed renewable integration for the financial burden. Pages 2–3 reproduce Regulation 7's volume-limit and additional-deviation-charge framework and the relaxation given by CERC's order of 20.1.2015 in Petition No. 6/RP/2015 for utilities with schedule of 400 MW or below.
Pages 3–7 record State concerns: Madhya Pradesh, Gujarat and Maharashtra seek higher or RE-adjusted deviation limits, compensation for RE-rich States, exclusion of infirm wind generation, and a graded limit scheme. The Commission's analysis rejects the larger proposals as unsafe for grid operation; explains that the 15% RE forecasting tolerance is not a licence to pass deviations to the State boundary; and points to load forecasting, RE forecasting, spinning reserves and ancillary services as the required response. It cites the Ancillary Services Operations Regulations of August 2015 and the suo-motu reserves order of 13.10.2015, and summarises the roadmap for reserves, AGC and a market-based ancillary services framework (pp5–7).
Pages 8–12 set out the proposed way forward. The medium-to-long-term roadmap covers load forecasting; intra-state deviation settlement, metering, accounting and software; RE forecasting and scheduling; State spinning reserves and ancillary services; faster intra-day trading; and cooperation with neighbouring States, with a 3–6 month implementation estimate (pp8–9). The transitional arrangement proposes State-wise DSM limits based on FY 2014-15 peak demand, following an L10-like model with higher percentage allowances for smaller States and caps for larger ones, valid from notification until 31.03.2017 and to be tightened after April 2017 (pp9–12). It clarifies that generating stations remain under the existing seller limits, and that a State selling as a regional entity is treated as a seller under Annexure III (p12).
Annexure I presents deviation trends for selected States (pp13–18). Annexure II, based on POSOCO's 2013-14 SCADA analysis, reports that State-boundary deviations correlate much more with demand and conventional generation changes than with wind variability (pp19–21). Annexure III explains NERC's CPS1, CPS2 and DCS balancing metrics and aligns the Indian volume-limit and zero-crossing concepts with them (p22).
Read with this
The regulation
Amendments and corrections
- Dated 17 Feb 2014Corrigendum to the Deviation Charges Notification, 6 January 2014
- Dated 18 Dec 2014Deviation Settlement Mechanism and related matters (First Amendment) Regulations, 2014
- Dated 7 Aug 2015Deviation Settlement Mechanism and related matters (Second Amendment) Regulations, 2015
- Dated 6 May 2016Deviation Settlement Mechanism and related matters Regulations, 2014 — Third Amendment, 2016
- Dated 20 Nov 2018Deviation Settlement Mechanism and related matters (Fourth Amendment) Regulations, 2018
- Dated 28 May 2019Deviation Settlement Mechanism and related matters Regulations, 2014 — Fifth Amendment, 2019
- Dated 12 Jun 2019Deviation Settlement Mechanism and Related Matters (Fifth Amendment) Regulations, 2019 — Errata
- Dated 5 Sep 2019Deviation Settlement Mechanism and Related Matters (Fourth Amendment) Regulations, 2018 — Erratum, 2019
Commencement notices and reasons
- Dated 5 Jan 2015Deviation Settlement Mechanism (First Amendment) Regulations, 2014 — Statement of Reasons
- Dated 6 May 2016Deviation Settlement Mechanism and Related Matters (Third Amendment) Regulations, 2016 — Statement of Reasons
- Dated 20 Nov 2018Deviation Settlement Mechanism and Related Matters (Fourth Amendment) Regulations, 2018 — Statement of Reasons
- Dated 12 Jun 2019Deviation Settlement Mechanism and Related Matters Regulations — Fifth Amendment, 2019 — Statement of Reasons
- Date not statedForecasting, Scheduling and Imbalance Handling for Wind and Solar, 2015 — Statement of Reasons
Procedures and orders made under it
- Dated 12 Aug 2014Start-up Power Drawal Procedure for New Generating Stations, 2014
- Dated 27 Mar 2020Deviation Settlement Mechanism (Fifth Amendment) Regulations, 2019 — Removal of Difficulties Order, 2020
- Date not statedProcedure for Implementation of the Framework on Forecasting, Scheduling and Imbalance Handling for Wind and Solar RE Generating Stations including Power Parks at Inter-State Level
Other copies of these documents (6)
- Dated 6 Jan 2014Deviation Settlement Mechanism and Related Matters Regulations, 2014
- Dated 18 Dec 2014Deviation Settlement Mechanism (First Amendment) Regulations, 2014
- Dated 7 Aug 2015Deviation Settlement Mechanism and related matters (Second Amendment) Regulations, 2015
- Dated 6 May 2016Deviation Settlement Mechanism and related matters, 2014 — Third Amendment, 2016
- Dated 20 Nov 2018Deviation Settlement Mechanism and related matters (Fourth Amendment) Regulations, 2018
- Dated 28 May 2019Deviation Settlement Mechanism and related matters (Fifth Amendment) Regulations, 2019
Earlier drafts
- Dated 20 Jun 2013Deviation Settlement Mechanism and related matters Regulations, 2013 — Draft
- Released with the notice dated 20 Jun 2013Explanatory memorandum: Explanatory Memorandum to Draft Deviation Settlement Mechanism Regulations, 2013
- Dated 20 Jun 2013Public notice: Draft Deviation Settlement Mechanism and related matters Regulations, 2013 — Public Notice
- Dated 24 Jun 2014Deviation Settlement Mechanism and Related Matters (First Amendment) Regulations, 2014 — Draft
- Released with the notice dated 23 Jun 2014Explanatory memorandum: Deviation Settlement Mechanism (First Amendment) Regulations, 2014 — Explanatory Memorandum — Draft
- Dated 23 Jun 2014Public notice: Deviation Settlement Mechanism (First Amendment) Regulations, 2014 — Public Notice — Draft
- Released with the notice dated 31 Mar 2015Deviation Settlement Mechanism and related matters (Second Amendment) Regulations, 2015 — Draft
- Dated 23 Oct 2015Deviation Settlement Mechanism and Related Matters, Third Amendment Regulations, 2015 — Draft
- Dated 23 Oct 2015Public notice: Deviation Settlement Mechanism and Related Matters (Third Amendment) Regulations, 2015 — Draft Public Notice
- Dated 29 Jun 2018Deviation Settlement Mechanism and related matters, 2014 — Fourth Amendment, 2018 — Draft
- Dated 29 Jun 2018Public notice: Draft Deviation Settlement Mechanism and related matters (Fourth Amendment) Regulations, 2018 — Public Notice
- Released with the notice dated 29 Jun 2018Explanatory memorandum: Deviation Settlement Mechanism and related matters Regulations, 2014 — Fourth Amendment, 2018 — Explanatory Memorandum
- Dated 18 Apr 2019Deviation Settlement Mechanism and related matters, 2014 — Fifth Amendment Regulations, 2019 — Draft
- Released with the notice dated 18 Apr 2019Explanatory memorandum: Explanatory Memorandum — Draft DSM (Fifth Amendment) Regulations, 2019
- Dated 18 Apr 2019Public notice: Draft Deviation Settlement Mechanism (Fifth Amendment) Regulations, 2019 — Public Notice
- Dated 3 May 2019Hearing notice: Public notice for public hearing on draft Deviation Settlement Mechanism (Fifth Amendment) Regulations, 2019
2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.