Deviation Settlement Mechanism and related matters, 2014 — Third Amendment, 2016

Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (Third Amendment) Regulations, 2016

Amendment · Gazette copyDated 6 May 2016Published in the Gazette 6 May 2016In force from 30 May 2016No.–L-1/(3)/2009-CERC.— dated 6th May, 2016

Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Deviation Settlement Mechanism and related matters Regulations, 2014 — Third Amendment, 2016.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the English text of CERC's Third Amendment to its 2014 Deviation Settlement Mechanism regulations. Issued on 6 May 2016 under section 178 of the Electricity Act 2003, it comes into force on 30 May 2016 (p5). The amendment creates a new regulatory category, the “Renewable Rich State”, defined as a State with at least 1000 MW combined installed wind and solar capacity, measured on the last day of the month for the next month (p5). It then rewrites the treatment of under-drawal and over-injection in Regulation 5, setting when deviation charges are zero and providing separate limits for Renewable Rich States (p5–6). It also adds a proviso on how deviation is calculated by RLDCs/RPCs and attributed by SLDCs to embedded entities (p5).

Regulation 7 is substantially revised: volume limits on over-drawal, under-drawal, under-injection and over-injection are tied to grid-frequency bands; a proviso exempting wind and solar regional entities is deleted and replaced; a new Table III for Renewable Rich States is added; Table I is retitled; and references to annexures are updated (p6–7). Regulation 7(2) retains exemptions for infirm injection before COD and start-up drawal (p6). The amendment amends the headings and provisos of Annexure I and II and inserts new Annexure I-A, II-A and III (p7). Annexure I-A gives the slab methodology for additional deviation charges payable by a Renewable Rich State for over-drawal/under-injection; Annexure II-A gives the parallel methodology for under-drawal/over-injection; Annexure III is the table of deviation limits for Renewable Rich States (p8–9). A note on p7 records the publication history of the Principal Regulations and earlier amendments.

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM)

Read with this

Other copies of these documents (5)

Earlier drafts

2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document