Procedure for Implementation of the Framework on Forecasting, Scheduling and Imbalance Handling for Wind and Solar RE Generating Stations including Power Parks at Inter-State Level

Procedure for implementation of the framework on Forecasting, Scheduling and Imbalance Handling for Renewable Energy (RE) Generating Stations including Power Parks based on wind and solar at Inter-State level

ProcedureDate not stated

Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Deviation Settlement Mechanism and related matters Regulations, 2014.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This CERC procedure sets out how forecasting, scheduling and imbalance handling for inter-state wind and solar generating stations, including power parks, is to be implemented. It is issued in compliance with Regulation 6.5(23) of the CERC Indian Electricity Grid Code Regulations, 2010 and the CERC Connectivity Regulations, and applies from the date of Commission notification, which is not printed (p2).

Scope binds NLDC, RLDCs, RPCs, SLDCs, RE generators and power parks, Lead Generators and Principal Generators (p2). Definitions cover Lead Generator, Principal Generator, RE Generator, Connection Point, Absolute Error and Available Capacity (AvC) (p3–4). Applicability is framed around RE regional entities, ISTS-connected RE with aggregate capacity of 50 MW and above, 5 MW to below 50 MW projects within an existing station, Lead/Principal Generators and solar/wind park developers (p5).

The operative sections allocate duties: RE generators/Lead/Principal must file one-time and updated data, day-ahead forecasts and schedules, real-time and monthly data, metering and commercial settlement, PPA-rate affidavits and indemnities (p5–7). RLDCs schedule, coordinate and may run forecasting, process meter data and engage forecasting agencies (p8–9). Connectivity applications follow the Connectivity Regulations, with park developers acting as nodal entities and sending SCADA data to RLDC/REMC (p9–11).

Scheduling and despatch covers 50 MW-and-above ISTS generators and aggregated sub-50 MW generators, with day-ahead 15-minute schedules, limited intra-day revisions and curtailment for system security (p11–12). Metering uses interface meters under CEA Metering Regulations and near-real-time telemetry (p13). RPCs do weekly energy accounting (p13–14); REC treatment nets deviations, allows notional RECs and purchase of solar/non-solar RECs to balance shortfalls (p14). Commercial settlement follows the DSM Second Amendment Regulations from 01.11.2015 and ECS (p14–15). Charges, losses, RLDC fees and a removal-of-difficulties clause follow (p15). Annexures provide registration/static data formats, day-ahead and current-day forecast formats, real-time telemetry lists and sample scheduling diagrams (p16–26).

Standard name
Grid Code, Connectivity and GNA Regulations, Forecasting, Scheduling and DSM for Wind and Solar
Primary topics
Scheduling and despatch, Deviation settlement (DSM), Energy accounting and settlement

Read with this

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.