Deviation Settlement Mechanism (First Amendment) Regulations, 2014 — Statement of Reasons

Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (First Amendment) Regulations, 2014 — Statement of Reasons

Statement of reasonsDated 5 Jan 2015

Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Deviation Settlement Mechanism and related matters Regulations, 2014 or one of its amendments.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This Statement of Reasons explains why the Commission amended its Deviation Settlement Mechanism Regulations, 2014 — and, just as importantly, which of its own draft proposals it abandoned after consultation. It opens with the consultation history: the Principal Regulations were notified on 6.1.2014, a corrigendum on 17.2.2014, and the draft First Amendment was published with an Explanatory Memorandum on the Commission's website on 23.06.2014, with comments due by 07.07.2014; 11 stakeholders, including POSOCO, WRPC, generators, state utilities and renewable generators, responded (p1).

Para 4 deals with Regulation 5. The fixed date that triggered uncapped deviation charges for CERC-regulated generating stations using APM gas is replaced by the date on which the Government of India actually revises APM gas prices, and the post-revision cap rate for infirm power injection during testing and commissioning is left to be notified separately by the Commission. No stakeholder objected (pp2–3).

Para 5 is the heart of the document. The draft had proposed deleting the provisos to Regulation 7(1) and 7(2)(i), which prohibit over-drawal/under-injection below 49.70 Hz and over-injection at or above 50.10 Hz. POSOCO opposed at length, invoking grid-disturbance history and the Enquiry Committee report; NTPC sought cleaner drafting plus generator exemptions (pp3–13). The Commission accepted POSOCO's argument, dropped the deletion, and instead amended Regulation 7(1) and 7(2) to widen the volume-limit band to 'and below 50.10 Hz' and to prohibit under-drawal and over-injection at or above that frequency (pp13–14). NTPC's exemption plea was rejected. Relaxation pleas from WIPPA (wind), TSECL and GRIDCO were declined as beyond the draft proposals and left to separate pending petitions (pp14–18).

Para 6 covers Annexure-II: the Para C illustration change will be issued as a corrigendum rather than as an amendment (pp18–19), and illustration 'A' is corrected so that under-drawal by a buyer or over-injection by a seller is treated as receivable rather than payable (pp20–21). Para 7 records Tata Power's compensation request on behalf of TPDDL for transmission outages and the Commission's refusal to consider it as unrelated to the amendment (pp21–23).

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM)

Read with this

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.