Deviation Settlement Mechanism and related matters (Fifth Amendment) Regulations, 2019

Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (Fifth Amendment) Regulations, 2019

Amendment · Gazette copyDated 28 May 2019In force from 3 Jun 2019No. L-1/132/2013-CERC dated 28th May, 2019

Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Deviation Settlement Mechanism and related matters Regulations, 2014 — Fifth Amendment, 2019.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's Fifth Amendment to the Deviation Settlement Mechanism (DSM) Regulations, 2014, notified as No. L-1/132/2013-CERC and dated 28 May 2019, in force from 3 June 2019 (p5).

The amendment does four things. It inserts two new definitions — "Daily Base DSM Charge" and "Time Block DSM Charge", both excluding Regulation 7 additional charges (p5). It amends Regulation 5 on charges for deviation: inter-regional deviation and cross-border transactions are to be priced on the unconstrained Day Ahead Market clearing price, and an entity spanning several bid areas is priced on the daily average ACP of the bid area carrying the largest share of its demand (p5). It replaces the old cap rate for generating stations with a flat cap of 303.04 Paise/kWh, expressly regardless of fuel type and of whether the station's tariff is Commission-regulated, and carries that same cap through Table-II of Regulation 7 and Annexure-I (pp6, 8).

Regulation 7 is reworked: a proviso is deleted, the additional-charge trigger for over-injection/under-drawal at 50.10 Hz and above is restated, and the sustained-deviation sign-change obligation is split into two phases — a 12-time-block window up to 31.03.2020 and a 6-time-block window from 01.04.2020 — with a graded additional-charge table, an exemptions list for renewables, run-of-river plant and others, and worked illustrations (pp6–8).

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Power markets and exchanges, Cross-border trade

Read with this

Other copies of these documents (5)

Earlier drafts

2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document