Deviation Settlement Mechanism and Related Matters (Third Amendment) Regulations, 2016 — Statement of Reasons

Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) (Third Amendment) Regulations, 2016

Statement of reasonsDated 6 May 2016

Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Deviation Settlement Mechanism and related matters Regulations, 2014 or one of its amendments.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Commission's Statement of Reasons, dated 6 May 2016 (p1), for the CERC (Deviation Settlement Mechanism and Related Matters) (Third Amendment) Regulations, 2016. It explains why the Commission decided what it did after the draft amendment was issued on 23 October 2015, comments closed on 16 November 2015 and a public hearing was held on 23 December 2015 (p1). It records the comments of the twenty stakeholders listed in Annexure-I (p20) and gives the Commission's analysis and decision on each.

The dominant issue is how state-wise DSM deviation limits should be set. The draft proposed limits proportional to peak demand met; wind- and solar-heavy states objected strongly. The Commission dropped the peak-demand basis and instead keeps existing DSM limits for all states except "renewable rich states", defined as states whose combined installed wind and solar capacity is 1000 MW or more (p5). Such states get relaxed limits in two bands according to combined installed capacity (p4). Capacity is reckoned as on the last day of a month for the following month, with RLDCs responsible for the assessment and generators and SLDCs required to report installations (p4–5). The relaxation is expressly a temporary measure pending better forecasting, scheduling and balancing and the roll-out of ancillary services (p4, p18).

Sections 2 and 3 (pp5–10) set out objections that the limits were too strict or ill-matched to import-dependent and small states (Kerala, Assam, UPPCL, TPDDL, MPPMCL); the Commission declined entity-specific revisions and confirmed that states continue to have a DSM limit at the state boundary. Section 4 (pp10–11) records requests to exempt forced outages and line tripping from additional deviation charges, held outside the scope of the amendment. Sections 5 and 6 (pp11–13) deal with the definition of "generating station" and the buyer/seller billing question, the latter referred to the State Commission.

Section 7 (pp13–19) collects miscellaneous comments — ACE monitoring, commercial penalties for zero-crossing violation, linking the 50 Hz deviation price to the day-ahead market, transmission reliability margin, harmonising the IEGC and DSM frequency bands, technical minimum and schedule-revision timelines — with reasons for deferring most of them. Three changes are accepted: an under-drawal tolerance for buyers with small schedules, mirroring the existing over-injection proviso and excluding renewable rich states (pp17–18); a modified proviso so RLDC/RPC calculate deviation for regional entities and SLDC attributes it to embedded entities (p17); and deletion of the Annexure-III note fixing deviation limits at a percentage of LTA+MTOA+STOA (p18). Annexure-II supplies the state-wise wind and solar capacity figures used to identify renewable rich states and is stated to be indicative only (pp5, 21–22).

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Scheduling and despatch, Ancillary services and reserves

Read with this

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.