Start-up Power Drawal Procedure for New Generating Stations, 2014

Procedure for drawal of Start-up Power for new Generating Stations, 2014

ProcedureDated 12 Aug 2014No. L-1/(93)/2009-CERC dated 12th August, 2014

Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Deviation Settlement Mechanism and related matters Regulations, 2014.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a CERC Secretary's letter of 12 August 2014 to the CEO of POSOCO recording that the Commission has approved the "Procedure for drawal of startup power for new generating stations, 2014" as an Annexure, and asking POSOCO to give it wide publicity (p1). The document therefore has two layers: the one-page approval letter and the operative Procedure and its formats.

The Procedure (p2–6) creates a route for a generating station still in its commissioning phase to draw start-up power from the Inter-State Transmission System through the Deviation Settlement Mechanism instead of contracting for it. It applies only where no unit of the station is already in commercial operation; if a unit is commissioned, the later units should normally take start-up power from it, unless that unit's output is fully allocated or committed under MTOA/LTA (p2). It states a scope binding on RLDCs, RPCs and generating stations including ISGS in the Seller category, and defines construction power, start-up power and auxiliary power to keep construction drawal out of this route (p2–3).

It then sets the pre-conditions a station must satisfy before applying — CTU connectivity, a signed Connection Agreement, established ISTS connectivity, commissioned switchyard equipment, data and voice communication with the RLDC, RPC-specified protection and GT/ST tap coordination (p3). It prescribes what the station must submit and undertake when applying (p3–5), the periodic data it must keep updating while drawing (p5), and the RLDC's role in granting, staggering, limiting or stopping drawal and in directing relays (p5–6). The maximum period for drawal is capped at 21 months from commencement of drawal — fifteen months before expected synchronisation and six months after — with any extension to be sought from CERC two months in advance (p6).

The remaining pages are blank formats: the application form (p7), the undertaking to be signed (p8–9) and the RLDC's grant of start-up power (p10). No commencement date, validity clause or repeal is stated; the text says only that the Commission has approved the Procedure.

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Grid operation and grid code, Payment security

Read with this

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document