CERC · Central Electricity Regulatory Commission

Deviation Settlement Mechanism and related matters Regulations, 2014 — Third Amendment, 2016

Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters)(Third Amendment) Regulations, 2016

AmendmentDated 6 May 2016In force from 30 May 2016No.–L-1/(3)/2009-CERC dated 6 th of May.2016

Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Deviation Settlement Mechanism and related matters Regulations, 2014.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Central Electricity Regulatory Commission issued this notification on 6 May 2016 as the Third Amendment to the CERC (Deviation Settlement Mechanism and related matters) Regulations, 2014 (p1). It comes into force on 30 May 2016, not on the issue date or on publication (p1). The centrepiece is a new category, 'Renewable Rich State', defined as a State whose minimum combined installed capacity of wind and solar power is 1000 MW or more, with capacity reckoned on the last day of the month for deciding the next month's status (p1).

Operatively, Regulation 2 adds a proviso making the concerned RLDC/RPC calculate deviation for Regional Entities, with SLDC attributing it to entities embedded in the State, and inserts the Renewable Rich State definition (p1). Regulation 5 substitutes the zero-charge provisos for under-drawal by buyers and over-injection by sellers beyond volume limits, carving out Renewable Rich States and referring them to Annexure-III; wind and solar generators that are regional entities are left to sub-clauses (v) to (vii) (p2). Regulation 7 is extensively amended: '(except Renewable Rich States)' is added to the buyer provision, a new proviso caps over-drawal/under-drawal by Renewable Rich States within Annexure-III limits in the normal frequency band, the old exemption proviso for wind and solar regional entities is deleted from Regulation 7(1) and a similar proviso is reinserted in Regulation 7(2), and Regulation 7(2) is substituted with seller volume limits, special Renewable Rich State limits, 400 MW schedule treatment, and exemptions for infirm injection before COD and start-up drawal (pp2–3). Table I is retitled and Table III for Renewable Rich States is added (pp3–4), as are Annexures I-A, II-A and III (pp4–5).

Pages 6–8 set methodologies for computing deviation charges and additional charges for Renewable Rich States: normal charges up to Annexure-III limits, graded additional charges above those limits, separate treatment for over-drawal/under-injection and under-drawal/over-injection, and frequency-specific consequences. Annexure-III maps combined wind and solar capacity bands to deviation limits (p9). A closing note lists the Principal Regulations' publication and prior corrigendum/first/second amendment dates (p5).

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM)

Read with this

Other copies of these documents (6)

Earlier drafts

2 more documents belong here and are not on Voltaic: 1 draft or notice on a draft and 1 draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.