Renewable Energy Certificate Regulations, 2010 — Fourth Amendment, 2016
Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) (Fourth Amendment) Regulations, 2016
AmendmentDated 28 Mar 2016No. L-1/12/2010-CERC dated 28 th March, 2016
Replaced by Renewable Energy Certificates for Renewable Energy Generation Regulations, 2022
See that regulation for the date it took effect and for anything it keeps in force.
Amends the Renewable Energy Certificate Regulations, 2010.
Summary
Summary written by software. Check the regulator's original before you rely on it.
What it is. A CERC notification dated 28 March 2016 (No. L-1/12/2010-CERC) making the Fourth Amendment to the CERC (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010. It is made under s.178 of the Electricity Act, 2003 and comes into force on publication in the Official Gazette; the Gazette date is not printed (p1).
Clause 2 — Regulation 5 (who may participate in the REC scheme). It deletes the second to sixth provisos and the explanation under Regulation 5(1)(c) and inserts fresh provisos in their place. The result is a self-contained eligibility rule for renewable generators selling the electricity component to a third party through open access: RECs on the entire generation are available only if the generator does not avail — or propose to avail — concessional/promotional transmission or wheeling charges or banking facility benefit. Where the generator forgoes such benefits voluntarily, eligibility begins only from the date of forgoing. The restriction does not apply where the SERC or State Government withdraws the benefits, and disputes over whether benefits were availed go to the Appropriate Commission. "Banking facility benefit" is defined narrowly, as banking that lets a generator use banked energy at any time including peak hours despite off-peak injection (p1–2).
Clause 2(3) — new Clause (1B). It covers captive generating plants and self-consumption renewable plants that do not meet the Electricity Rules, 2005 CGP test, barring RECs for self-consumed energy unless the plant was commissioned between 29 September 2010 and 31 March 2016 and registered with the Central Agency by 30 June 2016. Eligible plants must still avoid concessional transmission/wheeling or banking benefits, and face a three-year wait after voluntarily forgoing them — longer than the "date of forgoing" rule for open-access generators — with the same withdrawal exception and dispute route (p2–3).
Clause 3 — Regulation 8(3). Substituted so that an eligible renewable generator, including an eligible CGP, may retain certificates to offset its own renewable purchase obligation as a consumer, subject to certification and verification by the concerned State Agency (p3).
Note (p3) recites the Principal Regulations and the earlier First to Third Amendment Regulations and corrigendum with Gazette citations.
Read with this
The regulation
- Dated 14 Jan 2010Renewable Energy Certificate Regulations, 2010
Amendments and corrections
- Dated 29 Sep 2010REC (First Amendment) Regulations, 2010
- Dated 10 Jul 2013Renewable Energy Certificate (REC) (Second Amendment) Regulations, 2013
- Dated 30 Dec 2014Renewable Energy Certificate for Renewable Energy Generation Regulations, 2010 — Third Amendment, 2014
- Dated 27 Jan 2015Corrigendum to the Notification dated 30 December 2014 on Solar RECs, January 2015
- Dated 23 Mar 2016Renewable Energy Certificate Regulations, 2010 — Fourth Amendment, 2016
Commencement notices and reasons
- Dated 14 Jan 2010Renewable Energy Certificate Regulations, 2010 — Statement of Objects and Reasons
- Dated 27 Sep 2010Renewable Energy Certificate Regulations, 2010 — First Amendment — Statement of Objects and Reasons
- Dated 10 Jul 2013Renewable Energy Certificate (Second Amendment) Regulations, 2013 — Statement of Reasons
- Dated 30 Dec 2014Renewable Energy Certificate (Third Amendment) Regulations, 2014 — Statement of Reasons
- Dated 28 Mar 2016Renewable Energy Certificate Fourth Amendment Regulations, 2015 — Statement of Reasons
Procedures and orders made under it
- Dated 30 Dec 2014Determination of Forbearance and Floor Price for the Solar REC, 2014
- Date not statedDesignation of NLDC as Central Agency under the Renewable Energy Certificate Regulations
- Date not statedREC Procedures
Other copies of these documents (4)
- Dated 14 Jan 2010Renewable Energy Certificate for Renewable Energy Generation Regulations, 2010 — as amended
- Dated 29 Sep 2010Renewable Energy Certificate for Renewable Energy Generation Regulations, 2010 — First Amendment, 2010
- Dated 10 Jul 2013Renewable Energy Certificate Regulations, 2010 — Second Amendment, 2013
- Dated 30 Dec 2014Renewable Energy Certificate Regulations, 2010 — Third Amendment, 2014
Proposed changes (drafts with no final yet)
- Dated 26 Jun 2015Renewable Energy Certificate for Renewable Energy Generation (Fifth Amendment) Regulations, 2015 — Draft
- Dated 26 Jun 2015Public notice: Public Notice on Draft Renewable Energy Certificate (Fifth Amendment) Regulations, 2015
- Released with the notice dated 26 Jun 2015Explanatory memorandum: Renewable Energy Certificate (Fifth Amendment) Regulations, 2015 — Explanatory Memorandum — Draft
Earlier drafts
- Dated 2 Apr 2013Renewable Energy Certificate (Second Amendment) Regulations, 2013 — Draft
- Released with the notice dated 2 Apr 2013Explanatory memorandum: REC (Second Amendment) Regulations, 2012 — Explanatory Memorandum — Draft
- Dated 2 Apr 2013Public notice: REC (Second Amendment) Regulations, 2013 — Draft — Public Notice
- Dated 30 Sep 2014Renewable Energy Certificate for Renewable Energy Generation (Third Amendment) Regulations, 2014 — Draft
- Released with the notice dated 30 Sep 2014Explanatory memorandum: REC Third Amendment Regulations, 2014 — Explanatory Memorandum — Draft
- Dated 30 Sep 2014File: Solar REC Floor and Forbearance Price Order, 2014
- Dated 30 Sep 2014Public notice: Draft REC (Third Amendment) Regulations, 2014 and Solar REC Forbearance and Floor Price Order — Public Notice
- Released with the notice dated 31 Mar 2015Renewable Energy Certificate (Fourth Amendment) Regulations, 2015
- Dated 31 Mar 2015File: Proposed Framework for Forecasting, Scheduling & Imbalance Handling for Wind and Solar RE at Inter-State Level — Draft
- Dated 31 Mar 2015Public notice: Proposed Framework for Forecasting, Scheduling & Imbalance Handling for Wind and Solar RE Generating Stations at Inter-State Level — Public Notice, 2015
One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.