CERC · Central Electricity Regulatory Commission

Renewable Energy Certificate Regulations, 2010 — Fourth Amendment, 2016

Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) (Fourth Amendment) Regulations, 2016

AmendmentDated 23 Mar 2016F. No. L-1/12/2010-CERC dated 23rd March, 2016

Replaced by Renewable Energy Certificates for Renewable Energy Generation Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Renewable Energy Certificate Regulations, 2010.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's Fourth Amendment to its 2010 Renewable Energy Certificate (REC) regulations, notified in New Delhi on 23 March 2016 (p3). It takes effect from the date of publication in the Official Gazette, which is not printed in the pages available. It changes who may participate in the REC scheme in three ways.

Regulation 2 rewrites Regulation 5(1)(c) of the Principal Regulations (p3–4). It deletes the second to sixth provisos and the explanation, and inserts a fresh set: a renewable generator selling its electricity component to a third party through open access may claim RECs on its entire generation only if it does not avail, or propose to avail, concessional or promotional transmission/wheeling charges or banking facility benefit; a generator that forgoes those benefits on its own becomes eligible only from the date of forgoing; the condition falls away if the State Commission or State Government withdraws the benefits; and disputes about whether benefits were availed go to the Appropriate Commission. A new Clause (1B) makes renewable captive plants — including plants that do not meet the Electricity Rules, 2005 CGP tests but have self-consumption — ineligible for RECs on self-consumed energy if commissioned outside the 29 September 2010 – 31 March 2016 window or not registered with the Central Agency by 30 June 2016; those inside the window and registered in time may claim full generation, but face a three-year wait after forgoing benefits voluntarily.

Regulation 3 substitutes Regulation 8(3), allowing an eligible renewable generator or captive plant to retain certificates to offset its own renewable purchase obligation as a consumer, subject to State Agency certification and verification (p4). A closing Note lists the Principal Regulations and their earlier amendments and corrigendum (p4).

Standard name
REC Regulations
Primary topics
Renewable energy certificates (REC), Open access, Captive status

Read with this

The regulation

Other copies of these documents (4)

Proposed changes (drafts with no final yet)

One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document