CERC · Central Electricity Regulatory Commission

Renewable Energy Certificate (Third Amendment) Regulations, 2014 — Statement of Reasons

The Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) (Third Amendment) Regulations, 2014.

Statement of reasonsDated 30 Dec 2014

Replaced by Renewable Energy Certificates for Renewable Energy Generation Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Renewable Energy Certificate Regulations, 2010 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software, from pages 1 to 26 of 36. Check the regulator's original before you rely on it.

This is the Central Electricity Regulatory Commission's Statement of Reasons issued with the CERC (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) (Third Amendment) Regulations, 2014, dated 30 December 2014 (p1). It records the consultation on the draft amendment — public notice of 30 September 2014, 87 written comments received by 30 October 2014, and a public hearing on 10 November 2014 (p1–2) — then works issue by issue through the comments and the Commission's reasoning, quoting the final amending clauses.

Sections 1–2 set out the history of the REC framework (principal REC Regulations of 14 January 2010, plus the First and Second amendments) and list the five issues the third amendment was to address (p1–2).

Section 3 covers eligibility of distribution licensees for RECs on renewable energy procured beyond their RPO. The proposal is retained but tightened: past three years' shortfall, including waived or carried-forward RPO, must be adjusted first; a non-declining RPO proviso applies; certification from the Appropriate Commission is required; and the Central Agency is directed to frame an accreditation/registration procedure with timelines (p2–8).

Section 4 deals with the draft clause granting RECs for sale to the distribution licensee of the area at APPC or at the power exchange rate; it is kept in abeyance (p9–10).

Section 5, the longest, addresses the draft half-certificate multiplier for open access and captive generation. After a state-by-state revenue comparison the Commission keeps both multipliers in abeyance, states its intention to disallow CGPs from the REC scheme altogether, and directs staff to bring a fresh proposal (p10–19).

Section 6 replaces the draft's APPC-based vintage-multiplier formula with a floor-price ratio and confines it to solar generators registered before 1 January 2015, running from 1 January 2015 to 31 March 2017 (p20–24). Section 7 extends certificate validity to 1,095 days, with a saving for RECs that expired in FY 2014-15 and for certificates issued before the amendment takes effect, and protects certificates already issued even if accreditation is later revoked (p24–26). Section 8 begins miscellaneous comments on RPO compliance.

Standard name
REC Regulations
Primary topics
Renewable energy certificates (REC), Renewable purchase obligation (RPO / RCO), Open access

Read with this

The regulation

Other copies of these documents (4)

Proposed changes (drafts with no final yet)

One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.