Renewable Energy Certificate Regulations, 2010 — Second Amendment, 2013

Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) (Second Amendment) Regulations, 2013

Amendment · Gazette copyDated 10 Jul 2013Published in the Gazette 10 Jul 2013No. L‐1/12/2010‐CERC dated New Delhi, the 10th July, 2013

Replaced by Renewable Energy Certificates for Renewable Energy Generation Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Renewable Energy Certificate (REC) (Second Amendment) Regulations, 2013.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's Second Amendment to its Renewable Energy Certificate regulations, notified in the Gazette on 10 July 2013 (p1, p4). It rewrites the eligibility, application, trading and validity rules of the 2010 REC framework, whose publication date (18.1.2010) and first amendment (1.10.2010) are recorded in the closing Note (p7). It comes into force on Gazette publication (p4).

Eligibility (p4–6). Regulation 2(1)(k) is deleted. Regulation 5(1)(b) is replaced to bar RECs where the generator has a power purchase agreement for that capacity with an obligated entity at a tariff determined under s.62 or adopted under s.63, with a carve-out treating the distribution licensee's assessed/sanctioned connected load as the captive capacity of RE-based co-generation plants. Regulation 5(1)(c) is reworded around the pooled cost of power purchase as determined by the Appropriate Commission, and its old provisos are replaced by a set covering premature termination of a PPA (a bar of three years or till scheduled expiry, whichever is earlier), captive generating plants that have taken or forgone concessional transmission/wheeling or banking benefits, plants not meeting the Electricity Rules, 2005 CGP conditions, and referral of benefit disputes to the Appropriate Commission. A new sub-clause (d) excludes generation sold to an obligated entity for RPO compliance. 'Banking facility benefit' is defined in an Explanation.

Procedure and trading (p6). Regulation 7 sets a six-month application window from the corresponding generation, with applications on the 10th, 20th and last day of the month, and renames 'captive power producer' as 'captive generating plant'. Regulation 8 requires certificates to be dealt with only through a power exchange unless the Commission orders otherwise, and allows a renewable energy generator, including a CGP, to retain certificates to offset its own RPO as a consumer, subject to State Agency certification and verification, with a bar on offsetting group companies' RPO. Regulation 9 replaces 'preferential tariff' with the s.62/s.63 tariff formulation.

Validity (p6–7). Regulation 10 fixes issuance from the later of commercial operation or registration by the Central Agency, a certificate validity of 730 days, continued validity on later revocation of accreditation, and revocation with recovery plus interest at 2% over the SBI Base rate where accreditation was obtained on false or suppressed information.

Standard name
REC Regulations
Primary topics
Renewable energy certificates (REC), Renewable purchase obligation (RPO / RCO), Power markets and exchanges

Read with this

The regulation

Other copies of these documents (3)

Proposed changes (drafts with no final yet)

One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document