Supply Code and Performance Standards Seventh Amendment Regulations, 2025 — Corrigendum

Corrigendum to Supply Code and Performance Standards Seventh Amendment

CorrigendumDated 25 Jun 2025No. F.17(220)/DERC/Engg./2023-24/7898 dated the 25th June 2025

Corrects the Delhi Supply Code and Performance Standards Regulations, 2017 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

DERC's corrigendum of 25 June 2025 (p1) reworks the payment mechanism in Regulation 24(4)(iv) of the DERC (Supply Code and Performance Standards) (Seventh Amendment) Regulations, 2025, which had been notified on 2 June 2025. The trigger is capital works funded by a department of the Government of NCT of Delhi.

Three changes appear on page 1. Paragraph (2) of clause (iv)(c) is substituted so that the balance 70% plus applicable taxes is released against each completed stage or milestone, on invoice and completion report, with the concerned Delhi government department required to pay the discom promptly and in any case within a maximum of 45 days. Clause (iv)(d), which had allowed a working-capital interest component in the estimated cost, is deleted outright. A new Explanation under clause (iv)(e) makes the discom liable to refund the advance if the works are not completed, and routes recovery through Delhi Transco Ltd as nodal agency, which bills the discom and remits the proceeds to the department.

On page 2, clause (iv)(f) — which had made interest recoverable by the discom from the department for delay beyond 45 days — is also deleted, and all other provisions of the Seventh Amendment Regulations are left unchanged. The corrigendum is issued with the Commission's approval and states no separate commencement date.

Standard name
Electricity Supply Code, Standards of Performance
Primary topics
Capital cost and investment

Read with this

Procedures and orders made under it

3 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft.

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on derc.gov.in ↗

Report an issue with this document