DERC · Delhi Electricity Regulatory Commission
First Relaxation Order, 2017 — Supply Code and Performance Standards Regulations, 2017 (prepaid meters)
First Relaxation Order, 2017
OrderDated 10 Oct 2017F.17(174)/Engg./DERC/17-18/5851 dated 10.10.2017
Made under the Delhi Supply Code and Performance Standards Regulations, 2017.
Summary
Summary written by software. Check the regulator's original before you rely on it.
DERC's First Relaxation Order, 2017 (p1) is a one-page instrument that temporarily suspends the pre-payment-meter mandate in the Commission's 2017 Supply Code and Performance Standards Regulations. Regulations 11(4)(vi)(a) and 16(13) require that connections up to 45 kW, both for tenants and for applicants for temporary connection, be released only through pre-payment meters (p1). The requirement is new, and the distribution licensees said they lack enough meters and need more time for procurement, so the Commission uses Regulation 85 to keep those provisions in abeyance until 31.12.2017 and allows connections to be released through post-payment meters until then (p1). Clause 1 gives the short title and provides for commencement on the date of issue, 10.10.2017 (p1). The order does not restate or replace any other part of the 2017 Regulations.
Read with this
The regulation
- Dated 7 Jul 2017Delhi Supply Code and Performance Standards Regulations, 2017
Amendments and corrections
- Dated 2 Feb 2018Supply Code and Performance Standards (First Amendment) Regulations, 2018
- Dated 7 Mar 2018Supply Code and Performance Standards (First Amendment) Regulations, 2018 — Corrigendum
- Dated 25 Sep 2018Supply Code and Performance Standards Regulations, 2017 — Second Amendment, 2018
- Dated 18 Dec 2018Supply Code and Performance Standards (Third Amendment) Regulations, 2018
- Dated 24 May 2019Supply Code and Performance Standards, 2017 — Fourth Amendment, 2019
- Dated 16 Jul 2024Supply Code and Performance Standards Regulations, 2017 — Fifth Amendment, 2024
- Dated 2 Jun 2025Supply Code and Performance Standards Regulations, 2017 — Seventh Amendment, 2025
- Dated 25 Jun 2025Supply Code and Performance Standards Seventh Amendment Regulations, 2025 — Corrigendum
Commencement notices and reasons
- Dated 31 Jul 2017Schedule of Charges and Procedure under Supply Code and Performance Standards Regulations, 2017 — Statement of Reasons
- Date not statedSupply Code and Performance Standards Regulations, 2017 — Statement of Objects and Reasons
- Date not statedSchedule of Charges and the Procedure (Sixth Amendment) Order, 2021 — Explanatory Note
Procedures and orders made under it
- Dated 31 Aug 2017Schedule of Charges and Procedure under the Supply Code and Performance Standards Regulations, 2017 — Order
- Dated 27 Sep 2017Delhi Supply Code and Performance Standards (Removal of Difficulty) First Order, 2017
- Dated 28 Sep 2017Schedule of Charges and the Procedure (First Amendment) Order, 2017
- Dated 2 Feb 2018Schedule of Charges and the Procedure Order, 2017 — Second Amendment, 2018
- Dated 6 Feb 2018Delhi Electricity Supply Code and Performance Standards (Removal of Difficulty) Second Order, 2018
- Dated 26 Jun 2018Clarification on levy of temporary surcharge for unauthorised use of electricity, 2018
- Dated 4 Jul 2018Schedule of Charges and the Procedure (Third Amendment) Order, 2018
- Dated 5 Sep 2018Notification of Laboratory for Testing of Tampered Meters under Supply Code and Performance Standards Regulations, 2017 — Order, 2018
- Dated 24 Sep 2018Delhi Electricity Supply Code and Performance Standards (Removal of Difficulty) Third Order, 2018
- Dated 27 Feb 2019Manual of Practices for Handling Consumers' Complaints, 2019
- Dated 16 Apr 2019Manual of practice for handling consumer complaints — review of customer care centre timings
- Dated 31 May 2019Delhi Electricity Supply Code and Performance Standards (Relaxation) Second Order, 2019
- Dated 23 Oct 2019Schedule of Charges and the Procedure Order, 2017 — Fourth Amendment, 2019
- Dated 30 Dec 2019Schedule of Charges and the Procedure (Fifth Amendment) Order, 2019
- Dated 4 May 2020Delhi Electricity Supply Code and Performance Standards (Relaxation) Third Order, 2020
- Dated 25 Aug 2020Refund of Security Deposit and Other Credits on Termination of Connection — Clarification, 2020
- Dated 15 Apr 2021Schedule of Charges and the Procedure (Sixth Amendment) Order, 2021
- Dated 27 Apr 2021Suspension of Standards of Performance Order, 2021
- Dated 22 Jun 2021Revocation of Order dated 27.04.2021
- Dated 3 Feb 2022Order in the matter of Order dtd. 10/01/2022
- Dated 1 Jul 2026Delhi Electricity Supply Code and Performance Standards — Fourth Removal of Difficulty Order, 2026
- Date not statedNew Connection Application Form
Proposed changes (drafts with no final yet)
- Dated 5 Jul 2024Supply Code and Performance Standards (Sixth Amendment) Regulations 2024 — Draft
- Dated 2 Jul 2024Public notice: Public Notice — Draft Supply Code and Performance Standards (Sixth Amendment) Regulations, 2024
Earlier drafts
- Dated 20 Feb 2017Delhi Supply Code and Performance Standards Regulations, 2017 — Draft
- Dated 7 Jul 2017Draft Schedule of Charges and Procedure under Supply Code and Performance Standards Regulations, 2017
- Dated 1 Jan 2018Schedule of Charges and the Procedure (Third Amendment) Order, 2018 — Draft
- Dated 1 Jan 2018Public notice: Draft Schedule of Charges and the Procedure (Third Amendment) Order, 2018 — Public Notice
- Dated 4 Jul 2018Supply Code and Performance Standards Regulations, 2017 — Second Amendment, 2018 — Draft
- Dated 4 Jul 2018Public notice: Supply Code and Performance Standards, 2017 — Second Amendment, 2018 — Public Notice — Draft
- Dated 28 Feb 2019Supply Code and Performance Standards (Fourth Amendment) Regulations, 2019
- Dated 7 Jun 2024Supply Code and Performance Standards, 2017 — Fifth Amendment, 2024 — Draft
- Dated 7 Jun 2024Public notice: Supply Code and Performance Standards Regulations, 2017 — Fifth Amendment, 2024 — Public Notice on Draft
- Dated 1 May 2025Supply Code and Performance Standards Regulations, 2017 — Seventh Amendment, 2025 — Draft
- Dated 1 May 2025Public notice: Supply Code and Performance Standards Regulations, 2017 — Seventh Amendment, 2025 — Public Notice — Draft
3 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft.
Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.