DERC · Delhi Electricity Regulatory Commission
Schedule of Charges and the Procedure (Fifth Amendment) Order, 2019
OrderDated 30 Dec 2019F.17 (266)/DERC/Engg./2018-19/6330/ dated 30.12.2019
Made under the Delhi Supply Code and Performance Standards Regulations, 2017.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a short DERC amendment order, dated 30.12.2019, that rewrites the connection-charge clause of the Commission's 2017 Schedule of Charges and the Procedure Order. It substitutes Clause 5(3) of the Principal Order (p1) and applies only to applicants taking a new low-tension connection at a load of up to 200 kW/215 kVA under Regulation 21(2) of the Supply Code Regulations (p1).
The substituted clause lays down a slab table of normative SLD charges. For electrified areas it sets Rs.3000 for loads up to 5 kW and Rs.3000 plus Rs.500 per kW or kVA beyond 5 kW, limited to a maximum of Rs.15,000; road restoration charges are payable at actuals for the service line (p1). The table also carries an un-electrified-area row.
The second limb is retrospective. The difference between SLD charges collected from such LT applicants from 01.09.2017 at un-electrified-area rates and the SLD estimated at electrified-area rates applicable on the date of application is to be adjusted in the applicant's ensuing electricity bill (p2). The order is signed by the Chairperson; apart from the order date, no commencement date is stated (p1–2).
Read with this
The regulation
- Dated 7 Jul 2017Delhi Supply Code and Performance Standards Regulations, 2017
Amendments and corrections
- Dated 2 Feb 2018Supply Code and Performance Standards (First Amendment) Regulations, 2018
- Dated 7 Mar 2018Supply Code and Performance Standards (First Amendment) Regulations, 2018 — Corrigendum
- Dated 25 Sep 2018Supply Code and Performance Standards Regulations, 2017 — Second Amendment, 2018
- Dated 18 Dec 2018Supply Code and Performance Standards (Third Amendment) Regulations, 2018
- Dated 24 May 2019Supply Code and Performance Standards, 2017 — Fourth Amendment, 2019
- Dated 16 Jul 2024Supply Code and Performance Standards Regulations, 2017 — Fifth Amendment, 2024
- Dated 2 Jun 2025Supply Code and Performance Standards Regulations, 2017 — Seventh Amendment, 2025
- Dated 25 Jun 2025Supply Code and Performance Standards Seventh Amendment Regulations, 2025 — Corrigendum
Commencement notices and reasons
- Dated 31 Jul 2017Schedule of Charges and Procedure under Supply Code and Performance Standards Regulations, 2017 — Statement of Reasons
- Date not statedSupply Code and Performance Standards Regulations, 2017 — Statement of Objects and Reasons
- Date not statedSchedule of Charges and the Procedure (Sixth Amendment) Order, 2021 — Explanatory Note
Procedures and orders made under it
- Dated 31 Aug 2017Schedule of Charges and Procedure under the Supply Code and Performance Standards Regulations, 2017 — Order
- Dated 27 Sep 2017Delhi Supply Code and Performance Standards (Removal of Difficulty) First Order, 2017
- Dated 28 Sep 2017Schedule of Charges and the Procedure (First Amendment) Order, 2017
- Dated 10 Oct 2017First Relaxation Order, 2017 — Supply Code and Performance Standards Regulations, 2017 (prepaid meters)
- Dated 2 Feb 2018Schedule of Charges and the Procedure Order, 2017 — Second Amendment, 2018
- Dated 6 Feb 2018Delhi Electricity Supply Code and Performance Standards (Removal of Difficulty) Second Order, 2018
- Dated 26 Jun 2018Clarification on levy of temporary surcharge for unauthorised use of electricity, 2018
- Dated 4 Jul 2018Schedule of Charges and the Procedure (Third Amendment) Order, 2018
- Dated 5 Sep 2018Notification of Laboratory for Testing of Tampered Meters under Supply Code and Performance Standards Regulations, 2017 — Order, 2018
- Dated 24 Sep 2018Delhi Electricity Supply Code and Performance Standards (Removal of Difficulty) Third Order, 2018
- Dated 27 Feb 2019Manual of Practices for Handling Consumers' Complaints, 2019
- Dated 16 Apr 2019Manual of practice for handling consumer complaints — review of customer care centre timings
- Dated 31 May 2019Delhi Electricity Supply Code and Performance Standards (Relaxation) Second Order, 2019
- Dated 23 Oct 2019Schedule of Charges and the Procedure Order, 2017 — Fourth Amendment, 2019
- Dated 4 May 2020Delhi Electricity Supply Code and Performance Standards (Relaxation) Third Order, 2020
- Dated 25 Aug 2020Refund of Security Deposit and Other Credits on Termination of Connection — Clarification, 2020
- Dated 15 Apr 2021Schedule of Charges and the Procedure (Sixth Amendment) Order, 2021
- Dated 27 Apr 2021Suspension of Standards of Performance Order, 2021
- Dated 22 Jun 2021Revocation of Order dated 27.04.2021
- Dated 3 Feb 2022Order in the matter of Order dtd. 10/01/2022
- Dated 1 Jul 2026Delhi Electricity Supply Code and Performance Standards — Fourth Removal of Difficulty Order, 2026
- Date not statedNew Connection Application Form
Proposed changes (drafts with no final yet)
- Dated 5 Jul 2024Supply Code and Performance Standards (Sixth Amendment) Regulations 2024 — Draft
- Dated 2 Jul 2024Public notice: Public Notice — Draft Supply Code and Performance Standards (Sixth Amendment) Regulations, 2024
Earlier drafts
- Dated 20 Feb 2017Delhi Supply Code and Performance Standards Regulations, 2017 — Draft
- Dated 7 Jul 2017Draft Schedule of Charges and Procedure under Supply Code and Performance Standards Regulations, 2017
- Dated 1 Jan 2018Schedule of Charges and the Procedure (Third Amendment) Order, 2018 — Draft
- Dated 1 Jan 2018Public notice: Draft Schedule of Charges and the Procedure (Third Amendment) Order, 2018 — Public Notice
- Dated 4 Jul 2018Supply Code and Performance Standards Regulations, 2017 — Second Amendment, 2018 — Draft
- Dated 4 Jul 2018Public notice: Supply Code and Performance Standards, 2017 — Second Amendment, 2018 — Public Notice — Draft
- Dated 28 Feb 2019Supply Code and Performance Standards (Fourth Amendment) Regulations, 2019
- Dated 7 Jun 2024Supply Code and Performance Standards, 2017 — Fifth Amendment, 2024 — Draft
- Dated 7 Jun 2024Public notice: Supply Code and Performance Standards Regulations, 2017 — Fifth Amendment, 2024 — Public Notice on Draft
- Dated 1 May 2025Supply Code and Performance Standards Regulations, 2017 — Seventh Amendment, 2025 — Draft
- Dated 1 May 2025Public notice: Supply Code and Performance Standards Regulations, 2017 — Seventh Amendment, 2025 — Public Notice — Draft
3 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft.
Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.