Supply Code and Performance Standards, 2017 — Fifth Amendment, 2024 — Draft

Draft Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) (Fifth Amendment) Regulations, 2024

Draft amendmentDated 7 Jun 2024F.17(85)/DERC/Engg./2020-21/7022 dated 07.06.2024

Draft

A proposal that has since been finalised as the Supply Code and Performance Standards Regulations, 2017 — Fifth Amendment, 2024.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a short amending instrument from the Delhi Electricity Regulatory Commission — the Fifth Amendment to the DERC (Supply Code and Performance Standards) Regulations, 2017 — issued by the Commission's Secretary on 7 June 2024 under Regulation 87 of those Principal Regulations (p1). It is styled a draft, and its commencement clause ties its effect to publication in the official Gazette (p1).

The bulk of the change is definitional. Regulation 2(7) is replaced so that an "Application" counts as complete only when it is in the format the distribution licensee requires, with all requisite documents, charges and compliances (p1). A new "Metropolitan Area" definition is inserted at 2(42)(a), keyed to a population threshold and to a public notification by the Lt. Governor (p1). "Urban areas" at 2(51) becomes a residual category covering everything that is neither rural nor metropolitan (p1).

The operational change is in Regulation 11(4)(i), which sets maximum time periods for releasing a new connection or modifying an existing one from the existing distribution system in electrified areas, graded by metropolitan, urban and rural area and further split by whether road cutting permission or right of way is needed (p1–2). Illustrative tables show how the total time is built up in the two right-of-way scenarios (p2). Read the area definitions first: they decide which timeline applies.

Standard name
Electricity Supply Code, Standards of Performance
Primary topics
New connections and load changes, Conditions of supply

Read with this

Procedures and orders made under it

3 more documents belong here and are not on Voltaic: 3 drafts or notices on a draft.

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.