Open Access in inter-State Transmission Regulations, 2008 — Fifth Amendment, 2018 — Draft
Central Electricity Regulatory Commission (Open Access in inter-State Transmission) (Fifth Amendment) Regulations, 2018
Draft amendmentDated 8 Aug 2018No. PM/NOAR/2016/CERC dated 8 th August, 2018
Draft
A proposal that has since been finalised as the Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a draft amendment regulation issued by the Central Electricity Regulatory Commission on 8 August 2018 (p1). It would write a National Open Access Registry (NOAR) into the CERC (Open Access in inter-State Transmission) Regulations, 2008. It is styled a "Draft Amendment" and clause 1.2 states it takes effect only from a date the Commission notifies separately (p1).
Sections 2–3 add the definition of NOAR and a new Regulation 3A: a centralised electronic platform giving open access participants, trading licensees, power exchanges, NLDC/RLDCs/SLDCs and Regional Power Committees a single interface; automating short-term open access administration; and providing audit trails, a dashboard of applications, approvals and rejections, a repository, scheduling-software and power-exchange interfaces, a payment gateway and market-monitoring reports (p1–2). NOAR is to be owned and operated by NLDC (POSOCO), which must keep it cyber-secure, report compliance annually, review its operation and recover incremental costs under the RLDC fees and charges regulations (p2).
Sections 4–18 make NOAR the mandatory channel for the whole short-term open access workflow: the detailed procedure is to be issued by POSOCO with prior Commission approval after stakeholder consultation (p3); bilateral and collective transactions are processed through NOAR (new Regulation 5A, p3); applicants must register in NOAR, with a prescribed registration fee, validity period and renewal charge (new Regulation 5B, p3); and applications, acceptance or rejection, congestion-management bidding, schedule revisions, curtailment notices and all payments move onto the platform (pp3–8). The proviso to Regulation 7 is deleted (p4). Regulation 8 is replaced by a "Standing Clearance by Load Despatch Centre for Short Term Transactions" regime setting verification duties, issue and refusal timelines, a deemed-grant mechanism where the SLDC/RLDC does not answer a NOAR reminder, and consequences for exceeding the cleared quantum, including debarment and public listing of defaulters (pp4–6). A new proviso to Regulation 25A lets NLDC/RLDC deny short-term open access to an entity whose payment default exceeds 90 days from the due date, without approaching the Commission (p8). Section 19 moves open-access information-disclosure duties from NLDC/RLDC websites to NOAR (pp8–9), and a closing note lists the Principal Regulations and their amendment history (pp9–10).
Read with this
The regulation
- Dated 25 Jan 2008Open Access in inter-State Transmission Regulations, 2008
Amendments and corrections
- Dated 20 May 2009Open Access in inter-State Transmission (Amendment) Regulations, 2009
- Dated 10 Jun 2009Open Access in inter-State Transmission Regulations, 2008 — Corrigendum, 2009
- Dated 10 Jun 2009Open Access (Amendment) Regulations, 2009 — Corrigenda
- Dated 11 Sep 2013Open Access in inter-State Transmission (Second Amendment) Regulations, 2013
- Dated 12 May 2015Open Access in inter-State Transmission (Third Amendment) Regulations, 2015
- Dated 22 Jun 2016Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016
- Dated 2 Jan 2019Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018
- Dated 12 Dec 2019Open Access in inter-State Transmission (Sixth Amendment) Regulations, 2019
- Dated 20 Mar 2020Open Access Regulations, 2008 — Sixth Amendment — Commencement Notification, 2020
- Dated 15 Jun 2010Changes some provisions: Sharing of ISTS Charges and Losses Regulations, 2010
- Dated 15 Jun 2010Changes some provisions: Sharing of Inter State Transmission Charges and Losses Regulations, 2010
Commencement notices and reasons
- Dated 4 Mar 2008Open Access in Inter-State Transmission System Regulations, 2008 — Statement of Reasons
- Dated 1 Jul 2009Open Access in Inter-State Transmission Regulations, 2008 — 2009 Amendment — Statement of Reasons
- Dated 12 May 2015Open Access in inter-State Transmission (Third Amendment) Regulations, 2015 — Statement of Objects and Reasons
- Dated 12 Jul 2016Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016 — Statement of Objects and Reasons
- Dated 2 Jan 2019Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018 — Statement of Reasons
- Dated 21 Mar 2022Notification — effective date 01.05.2022
- Dated 21 Mar 2022Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018 — Commencement Notification
- Date not statedReal-Time Market Framework — Statement of Reasons
Procedures and orders made under it
- Dated 1 Apr 2022Approval of Procedure for Short Term Open Access in inter-State Transmission System through NOAR, 2022
- Dated 1 Apr 2022Short Term Open Access in Inter-State Transmission through NOAR — Procedure, 2022
- Dated 6 May 2022Corrigendum to the NOAR STOA Procedure Order, 2022
- Date not statedProcedure for Short Term Open Access in inter-State Transmission System through NOAR, 2022
Other copies of these documents (6)
- Dated 25 Jan 2008Open Access in inter-State Transmission Regulations, 2008
- Dated 11 Sep 2013Open Access in inter-State Transmission Regulations, 2008 — Second Amendment, 2013
- Dated 12 May 2015Open Access in inter-State Transmission (Third Amendment) Regulations, 2015
- Dated 22 Jun 2016Open Access in inter-State Transmission (Fourth Amendment) Regulations, 2016
- Dated 2 Jan 2019Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018
- Dated 12 Dec 2019Open Access in inter-State Transmission Regulations, 2008 — Sixth Amendment, 2019
Earlier drafts
- Dated 3 Jul 2014Open Access in inter-State Transmission Regulations, 2008 — Third Amendment, 2014 — Draft
- Dated 3 Jul 2014Public notice: Open Access in inter-State Transmission (Third Amendment) Regulations, 2014 — Public Notice — Draft
- Released with the notice dated 3 Jul 2014Explanatory memorandum: Open Access in inter-State Transmission, 2008 — Third Amendment, 2014 — Explanatory Memorandum — Draft
- Dated 3 May 2016Open Access in inter-State Transmission, 2008 — Fourth Amendment, 2016 — Draft
- Dated 3 May 2016Public notice: Open Access in inter-State Transmission, 2008 — Fourth Amendment, 2016 — Public Notice — Draft
- Released with the notice dated 3 May 2016Explanatory memorandum: Open Access in Inter-state Transmission (Fourth Amendment) Regulations, 2016 — Explanatory Memorandum — Draft
- Dated 6 Aug 2019Open Access in inter-State Transmission Regulations, 2008 — Sixth Amendment, 2019 — Draft
- Released with the notice dated 6 Aug 2019Explanatory memorandum: Real-Time Markets for Electricity — Explanatory Memorandum
- Released with the notice dated 8 Aug 2018Explanatory memorandum: Open Access in inter-State Transmission, 2008 — Fifth Amendment — Draft Explanatory Memorandum
- Dated 8 Aug 2018Public notice: Draft Open Access in inter-State Transmission (Fifth Amendment) Regulations, 2018 — Public Notice
2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.